Laurel Wind Energy Center
ERCOT queue ID 27INR0056
Laurel Wind Energy Center (27INR0056) is listed in the ERCOT interconnection queue as a 306.6 MW wind project in Pecos County, TX. The filing names Tap Solstice to Bakersfield (Bus# -) Ckt 2 and Tap Solstice to Bakersfield (Bus# -) Ckt 1 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on September 22, 2023, the full interconnection study as approved on September 29, 2026 and the interconnection agreement as signed on October 25, 2024.
| Queue ID | 27INR0056 |
|---|---|
| Project name | Laurel Wind Energy Center |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Solstice to Bakersfield (Bus# -) Ckt 2 and Tap Solstice to Bakersfield (Bus# -) Ckt 1 |
| Point of interconnection | Tap Solstice to Bakersfield (Bus# 60404 -76002) 345kV Ckt 2 and Tap Solstice to Bakersfield (Bus# 60404 -76002) 345kV Ckt 1 |
| County | Pecos |
| State | TX |
| Voltage | 345 kV |
| Capacity | 306.6 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-09 | Status change | n/a | SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA |
Additional filed fields
| Interconnecting entity | LAUREL ENERGY CENTER, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | WIN |
| Technology code | WT |
| Interconnection agreement signed | 2024-10-25 |
| Screening study complete | 2023-09-22 |
| Full interconnection study approved | 2026-09-29 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.