Substation Scout

Keys Hollow Solar Phase II SLF

ERCOT queue ID 24INR0065

Queue ID24INR0065
Project nameKeys Hollow Solar Phase II SLF
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Coleto Creek - RAPTOR7A
Point of interconnection345kV Tap 8164 Coleto Creek - 8673 RAPTOR7A
CountyGoliad
StateTX
Voltage345 kV
Capacity200.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-03-10
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting EntityKeys Hollow Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Ia Signed45594
Screening Study Complete44440
Fis Approved46267
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.