Crossroads Wind

ERCOT queue ID 26INR0021

Crossroads Wind (26INR0021) is listed in the ERCOT interconnection queue as a 277.4 MW wind project in Victoria County, TX. The filing names Dokmai as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of February 28, 2028. It records the screening study as complete on December 22, 2022, the full interconnection study as approved on May 28, 2026 and the interconnection agreement as signed on July 24, 2024.

Queue ID26INR0021
Project nameCrossroads Wind
Status (as published)SS Completed, FIS Completed, IA
SubstationDokmai
Point of interconnection80090 Dokmai 138 KV
CountyVictoria
StateTX
Voltage138 kV
Capacity277.4 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2028-02-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Victoria, TX: 22 requests in the ERCOT queue, 17 active totaling 5,382.9 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Capacity revised +0.6 SS Completed, FIS Completed, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityHyFuels Green Lake Wind LLC
CDR reporting zoneSOUTH
Fuel codeWIN
Technology codeWT
Interconnection agreement signed2024-07-24
Screening study complete2022-12-22
Full interconnection study approved2026-05-28
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.