Juno 3 Solar
ERCOT queue ID 26INR0621
| Queue ID | 26INR0621 |
|---|---|
| Project name | Juno 3 Solar |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | # Buck Canyon |
| Point of interconnection | #59916 Buck Canyon 345kV |
| County | Borden |
| State | TX |
| Voltage | 345 kV |
| Capacity | 500 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2027-11-30 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Juno Solar 3 |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45839 |
| Screening Study Complete | 45817 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.