Operation Sunshine Storage
ERCOT queue ID 26INR0357
| Queue ID | 26INR0357 |
|---|---|
| Project name | Operation Sunshine Storage |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Amos Creek |
| Point of interconnection | 7077 Amos Creek 345kV |
| County | Concho |
| State | TX |
| Voltage | 345 kV |
| Capacity | 409.8 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2029-04-01 |
| Source dataset | large |
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-09-07 | Status change | n/a | Inactive → SS Completed, FIS Started, IA |
Additional filed fields
| Interconnecting Entity | Duck Creek Storage, LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Ia Signed | 45896 |
| Screening Study Complete | 45331 |
| Air Permit | Not Required |