Substation Scout

Bigway Solar I

ERCOT queue ID 27INR0127

Queue ID27INR0127
Project nameBigway Solar I
Status (as published)SS Completed, FIS Started, IA
SubstationTap Cottonwood - Edith Clarke Ckt #2
Point of interconnectionTap 345kV 59904 Cottonwood - 60500 Edith Clarke Ckt #2
CountyKing
StateTX
Voltage345 kV
Capacity195.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityNextEra Energy Interconnection Holdings, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Ia Signed45703
Screening Study Complete45366
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.