Victory Ellis – Gas

ERCOT queue ID 29INR0264

Victory Ellis – Gas (29INR0264) is listed in the ERCOT interconnection queue as a 465.9 MW gas project in Ellis County, TX. The filing names Tap Nimbus – Big Onion & Stainback – Elrod Switch DCKT as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 28, 2030. It records the screening study as complete on August 18, 2026.

Queue ID29INR0264
Project nameVictory Ellis – Gas
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Nimbus – Big Onion & Stainback – Elrod Switch DCKT
Point of interconnectionTap 345kV Nimbus (2249) – Big Onion (2466) & Stainback (2217) – Elrod Switch (3159) DCKT
CountyEllis
StateTX
Voltage345 kV
Capacity465.9 MW
Resource (as published)GAS/GT
Resource categoryGas (normalized for filtering)
Target commercial operation2030-09-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Nimbus – Big Onion & Stainback – Elrod Switch DCKT substation: 2 requests in the ERCOT queue, 2 active totaling 918.9 MW.

Queue IDProjectMWResourceStatus
28INR0529Victory Ellis–BESS453BatterySS Completed, FIS Started, No IA

Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Status change n/a SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting entityVictory Ellis, LLC
CDR reporting zoneNORTH
Fuel codeGAS
Technology codeGT
Screening study complete2026-08-18

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.