Cedar Draw BESS
ERCOT queue ID 27INR0193
| Queue ID | 27INR0193 |
|---|---|
| Project name | Cedar Draw BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Nebula7A |
| Point of interconnection | 60011 Nebula7A 345kV |
| County | Scurry |
| State | TX |
| Voltage | 345 kV |
| Capacity | 225.7 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Cedar Draw Solar LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45462 |