Megamouth Energy Storage
ERCOT queue ID 26INR0341
Megamouth Energy Storage (26INR0341) is listed in the ERCOT interconnection queue as a 101.3 MW battery project in Harris County, TX. The filing names Mykawa as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on June 19, 2024, the full interconnection study as approved on September 17, 2024 and the interconnection agreement as signed on November 18, 2025.
| Queue ID | 26INR0341 |
|---|---|
| Project name | Megamouth Energy Storage |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Mykawa |
| Point of interconnection | 42750 Mykawa 138 kV |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 101.3 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.
Tracked changes
2 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Status change | n/a | Inactive → SS Completed, FIS Completed, IA |
| 2026-09-07 | Terminal status | 101.3 | SS Completed, FIS Completed, IA → Inactive |
Additional filed fields
| Interconnecting entity | GCI Megamouth, LLC |
|---|---|
| CDR reporting zone | HOUSTON |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-11-18 |
| Screening study complete | 2024-06-19 |
| Full interconnection study approved | 2024-09-17 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.