Darkwood Solar
ERCOT queue ID 27INR0049
| Queue ID | 27INR0049 |
|---|---|
| Project name | Darkwood Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Comanche Peak to Comanche SS |
| Point of interconnection | Tap 345KV 1900 Comanche Peak to 1440 Comanche SS |
| County | Comanche |
| State | TX |
| Voltage | 345 kV |
| Capacity | 152 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2027-09-20 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Mustang Creek Solar, LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45966 |
| Screening Study Complete | 45170 |
| Fis Approved | 45867 |
| Water Availability | Not Required |