Substation Scout

Newville-Nottingham Tap 1 69 kV

PJM queue ID AG2-166

Queue IDAG2-166
Project nameNewville-Nottingham Tap 1 69 kV
Status (as published)Active
SubstationNewville-Nottingham Tap 1
Point of interconnectionNewville-Nottingham Tap 1 69 kV
CountyCumberland
StatePA
Voltage69 kV
Capacity10 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

DeveloperCosten Solar, Inc
Transmission OwnerPPL
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy10.0
Mfo10.0
Submitted Date2/25/2021
Last Updated5/14/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.