Rattler Combined Cycle Energy Center I

ERCOT queue ID 29INR0410

Rattler Combined Cycle Energy Center I (29INR0410) is listed in the ERCOT interconnection queue as a 990.6 MW gas project in Cameron County, TX. The filing names RIOHONDO7A Substation as its point of interconnection. ERCOT lists its status as “SS Started, FIS Started, No IA”, with a target commercial operation date of May 15, 2029.

Queue ID29INR0410
Project nameRattler Combined Cycle Energy Center I
Status (as published)SS Started, FIS Started, No IA
SubstationRIOHONDO7A Substation
Point of interconnection345kV 8318 RIOHONDO7A Substation
CountyCameron
StateTX
Voltage345 kV
Capacity990.6 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2029-05-15
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

RIOHONDO7A Substation substation: 3 requests in the ERCOT queue, 3 active totaling 2,971.8 MW.

Queue IDProjectMWResourceStatus
29INR0415Rattler Combined Cycle Energy Center II990.6GasSS Started, FIS Started, No IA
29INR0416Rattler Combined Cycle Energy Center III990.6GasSS Started, FIS Started, No IA

Cameron, TX: 32 requests in the ERCOT queue, 30 active totaling 8,649.9 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 New request 990.6 Not reported → SS Started, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting entityBlack Mountain Energy Storage II
CDR reporting zoneCOASTAL
Fuel codeGAS
Technology codeCC

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first