Seine BESS
ERCOT queue ID 23INR0140
Seine BESS (23INR0140) is listed in the ERCOT interconnection queue as a 308.9 MW battery project in Foard County, TX. The filing names Edith Clarke as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of October 1, 2027. It records the screening study as complete on February 19, 2021, the full interconnection study as approved on September 1, 2026 and the interconnection agreement as signed on December 1, 2024.
| Queue ID | 23INR0140 |
|---|---|
| Project name | Seine BESS |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Edith Clarke |
| Point of interconnection | 60500 Edith Clarke 345kV |
| County | Foard |
| State | TX |
| Voltage | 345 kV |
| Capacity | 308.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-10-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Foard, TX: 5 requests in the ERCOT queue, 5 active totaling 1,593.9 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Status change | n/a | SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA |
Additional filed fields
| Interconnecting entity | BRP Seine BESS LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2024-12-01 |
| Screening study complete | 2021-02-19 |
| Full interconnection study approved | 2026-09-01 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.