Substation Scout

Las Mujeres Solar

ERCOT queue ID 29INR0154

Queue ID29INR0154
Project nameLas Mujeres Solar
Status (as published)SS Started, FIS Started, No IA
SubstationCruces 7A (Bus #)
Point of interconnectionCruces 7A (Bus #80079)
CountyJim Hogg
StateTX
VoltageNot reported
Capacity684.3 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-01
Source datasetlarge

Additional filed fields

Interconnecting EntityLas Mujeres Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.