Substation Scout

Cedar Range Solar

ERCOT queue ID 25INR0204

Queue ID25INR0204
Project nameCedar Range Solar
Status (as published)SS Completed, FIS Completed, IA
Substation“Sweet Tea” switchyard that taps the Allen Switch – Stouts Creek Line
Point of interconnection“Sweet Tea” 345 kV switchyard that taps the Allen Switch – Stouts Creek 345 kV Line
CountyHopkins
StateTX
Voltage345 kV
Capacity150.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-09-17
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting EntityCedar Range, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Ia Signed45840
Screening Study Complete44914
Fis Approved46282
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.