Skull Creek Solar (23INR0289) is listed in the ERCOT interconnection queue as a 137 MW solar project in Anderson County, TX. The filing names Tap Tennessee Colony - Blackfoot Massey Lake Switch in TSP’s Pin Oak Switch - Long Lake Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of June 30, 2027. It records the screening study as complete on August 19, 2021, the full interconnection study as approved on September 18, 2026 and the interconnection agreement as signed on May 20, 2024.
| Queue ID | 23INR0289 |
|---|---|
| Project name | Skull Creek Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Tennessee Colony - Blackfoot Massey Lake Switch in TSP’s Pin Oak Switch - Long Lake Substation |
| Point of interconnection | Tap 138kV 3281 Tennessee Colony - 3499 Blackfoot Massey Lake Switch in TSP’s Pin Oak Switch - Long Lake Substation |
| County | Anderson |
| State | TX |
| Voltage | 138 kV |
| Capacity | 137 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-06-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Anderson, TX: 9 requests in the ERCOT queue, 9 active totaling 4,644.7 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Status change | n/a | SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA |
Additional filed fields
| Interconnecting entity | Skull Creek Solar, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2024-05-20 |
| Screening study complete | 2021-08-19 |
| Full interconnection study approved | 2026-09-18 |
| Air permit | Not Required |
| Water availability | Not Required |