Substation Scout

H&C WILBARGER POWER II

ERCOT queue ID 32INR0008

H&C WILBARGER POWER II (32INR0008) is listed in the ERCOT interconnection queue as a 1,025.6 MW gas project in Wilbarger County, TX. The filing names Tap RILEY7A - EDITHCLA7B as its point of interconnection. ERCOT lists its status as “SS Started, FIS Started, No IA”, with a target commercial operation date of February 27, 2032.

Queue ID32INR0008
Project nameH&C WILBARGER POWER II
Status (as published)SS Started, FIS Started, No IA
SubstationTap RILEY7A - EDITHCLA7B
Point of interconnectionTap 345kV 6101 RILEY7A - 60505 EDITHCLA7B
CountyWilbarger
StateTX
Voltage345 kV
Capacity1,025.6 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2032-02-27
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap RILEY7A - EDITHCLA7B substation: 6 requests in the ERCOT queue, 6 active totaling 3,256.5 MW.

Queue IDProjectMWResourceStatus
32INR0006H&C WILBARGER POWER I1,025.6GasSS Started, FIS Started, No IA
29INR0148Big Field Solar506.2SolarSS Completed, FIS Started, No IA
28INR0476Pease River Solar276.4SolarSS Completed, FIS Started, No IA
28INR0464Grayback Solar221.8SolarSS Completed, FIS Started, No IA
28INR0535Daisy Solar200.9SolarSS Completed, FIS Started, No IA

Wilbarger, TX: 24 requests in the ERCOT queue, 21 active totaling 8,450.9 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 New request 1,025.6 Not reported → SS Started, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting entityH&C WILBARGER POWER I
CDR reporting zoneWEST
Fuel codeGAS
Technology codeCC

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first