Waterloo Solar 1

ERCOT queue ID 25INR0422

Waterloo Solar 1 (25INR0422) is listed in the ERCOT interconnection queue as a 201.3 MW solar project in Bastrop County, TX. The filing names Tap 345-kV Austrop to Zorn as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 1, 2027. It records the screening study as complete on July 12, 2023, the full interconnection study as approved on September 18, 2026 and the interconnection agreement as signed on September 4, 2024.

Queue ID25INR0422
Project nameWaterloo Solar 1
Status (as published)SS Completed, FIS Completed, IA
SubstationTap 345-kV Austrop to Zorn
Point of interconnectionTap 345-kV 7040 Austrop to 7042 Zorn
CountyBastrop
StateTX
VoltageNot reported
Capacity201.3 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-12-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap 345-kV Austrop to Zorn substation: 2 requests in the ERCOT queue, 2 active totaling 321.3 MW.

Queue IDProjectMWResourceStatus
25INR0447Waterloo BESS 1120BatterySS Completed, FIS Started, IA

Bastrop, TX: 16 requests in the ERCOT queue, 14 active totaling 5,098.7 MW.

Tracked changes

2 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 Capacity revised +0.7 SS Completed, FIS Completed, IA → SS Completed, FIS Completed, IA
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityWaterloo Solar I, LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2024-09-04
Screening study complete2023-07-12
Full interconnection study approved2026-09-18
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.