Sol Marina SLF Energy Center

ERCOT queue ID 26INR0241

Queue ID26INR0241
Project nameSol Marina SLF Energy Center
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Stainback Switch (bus# ) – Big Onion Switch (bus# )
Point of interconnectionTap 345kV Stainback Switch (bus# 2217) – Big Onion Switch (bus# 2466)
CountyEllis
StateTX
Voltage345 kV
Capacity171.1 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-10-29
Source datasetlarge

Tracked changes

3 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA
2026-09-07 Capacity revised −4.2 SS Completed, FIS Completed, IA → SS Completed, FIS Started, IA
2026-09-07 Status change n/a SS Completed, FIS Completed, IA → SS Completed, FIS Started, IA

Full change log →

Additional filed fields

Interconnecting EntitySol Marina Energy Center, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Ia Signed45772
Screening Study Complete45313
Fis Approved46282
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.