Sol Marina SLF Energy Center

ERCOT queue ID 26INR0241

Sol Marina SLF Energy Center (26INR0241) is listed in the ERCOT interconnection queue as a 171.1 MW solar project in Ellis County, TX. The filing names Tap Stainback Switch (bus# ) – Big Onion Switch (bus# ) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of October 29, 2027. It records the screening study as complete on January 22, 2024, the full interconnection study as approved on September 17, 2026 and the interconnection agreement as signed on April 25, 2025.

Queue ID26INR0241
Project nameSol Marina SLF Energy Center
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Stainback Switch (bus# ) – Big Onion Switch (bus# )
Point of interconnectionTap 345kV Stainback Switch (bus# 2217) – Big Onion Switch (bus# 2466)
CountyEllis
StateTX
Voltage345 kV
Capacity171.1 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-10-29
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.

Tracked changes

3 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA
2026-09-07 Capacity revised −4.2 SS Completed, FIS Completed, IA → SS Completed, FIS Started, IA
2026-09-07 Status change n/a SS Completed, FIS Completed, IA → SS Completed, FIS Started, IA

Full change log →

Additional filed fields

Interconnecting entitySol Marina Energy Center, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2025-04-25
Screening study complete2024-01-22
Full interconnection study approved2026-09-17
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.