TOCE BESS 1
ERCOT queue ID 25INR0293
TOCE BESS 1 (25INR0293) is listed in the ERCOT interconnection queue as a 205.2 MW battery project in Wharton County, TX. The filing names Danevang Switching Station (Bus# ) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on January 10, 2024, the full interconnection study as approved on November 7, 2024 and the interconnection agreement as signed on December 30, 2024.
| Queue ID | 25INR0293 |
|---|---|
| Project name | TOCE BESS 1 |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Danevang Switching Station (Bus# ) |
| Point of interconnection | 138 kV Danevang Switching Station (Bus# 5546) |
| County | Wharton |
| State | TX |
| Voltage | 138 kV |
| Capacity | 205.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | TOCE BESS 1, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2024-12-30 |
| Screening study complete | 2024-01-10 |
| Full interconnection study approved | 2024-11-07 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.