Substation Scout

Realitos Solar SLF

ERCOT queue ID 26INR0196

Queue ID26INR0196
Project nameRealitos Solar SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationBruni (#) – Crestonio (#) line; AEP
Point of interconnectionBruni (#8297) – Crestonio (#8695) 138 kV line; AEP
CountyDuval
StateTX
Voltage138 kV
Capacity150.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-15
Source datasetlarge

Additional filed fields

Interconnecting EntityMesquite Creek LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45265
Air PermitNot Required
Water AvailabilityNot Required