Substation Scout

Starfield Energy Storage

ERCOT queue ID 30INR0133

Starfield Energy Storage (30INR0133) is listed in the ERCOT interconnection queue as a 122.2 MW battery project in Wharton County, TX. The filing names Tap Hungerford - East Bernard as its point of interconnection. ERCOT lists its status as “SS Started, FIS Started, No IA”, with a target commercial operation date of December 31, 2030.

Queue ID30INR0133
Project nameStarfield Energy Storage
Status (as published)SS Started, FIS Started, No IA
SubstationTap Hungerford - East Bernard
Point of interconnectionTap 138kV 44150 Hungerford - 44190 East Bernard
CountyWharton
StateTX
Voltage138 kV
Capacity122.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2030-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 New request 122.2 Not reported → SS Started, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting entityStarfield Energy Storage, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.