ERCOT queue ID 30INR0058

Springfield Solar (30INR0058) is listed in the ERCOT interconnection queue as a 400 MW solar project in Pecos County, TX. The filing names Tap Leon Creek (#) to Woodhouse Station (#) line as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of August 30, 2028. It records the screening study as complete on October 15, 2025 and the interconnection agreement as signed on December 24, 2025.

Queue ID30INR0058
Project nameSpringfield Solar
Status (as published)SS Completed, FIS Started, IA
SubstationTap Leon Creek (#) to Woodhouse Station (#) line
Point of interconnectionTap Leon Creek (#38355) to Woodhouse Station (#38308) 138kV line
CountyPecos
StateTX
Voltage138 kV
Capacity400 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-08-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBOULEVARD ASSOCIATES, LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Interconnection agreement signed2025-12-24
Screening study complete2025-10-15
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first