Zora Solar
ERCOT queue ID 29INR0197
Zora Solar (29INR0197) is listed in the ERCOT interconnection queue as a 250.8 MW solar project in Wharton County, TX. The filing names Athena as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of October 15, 2029. It records the screening study as complete on August 10, 2026.
| Queue ID | 29INR0197 |
|---|---|
| Project name | Zora Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Athena |
| Point of interconnection | 46650 Athena 138 kV |
| County | Wharton |
| State | TX |
| Voltage | 138 kV |
| Capacity | 250.8 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-10-15 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-09-07 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
Additional filed fields
| Interconnecting entity | Zora Solar, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2026-08-10 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.