Walnut Solar I

PJM queue ID AE1-004

Queue IDAE1-004
Project nameWalnut Solar I
Status (as published)Partially in Service - Under Construction
SubstationHarmony Village-Shackleford
Point of interconnectionHarmony Village-Shackleford 115 kV
CountyKing and Queen
StateVA
Voltage115 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-07-14
Source datasetserial

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a Under Construction → Partially in Service - Under Construction

Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo110

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.