Ashtrom Marigold BESS SLF
ERCOT queue ID 29INR0324
Ashtrom Marigold BESS SLF (29INR0324) is listed in the ERCOT interconnection queue as a 153.9 MW battery project in Pecos County, TX. The filing names 860 GIRVINSW as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 26, 2029. It records the screening study as complete on October 3, 2026.
| Queue ID | 29INR0324 |
|---|---|
| Project name | Ashtrom Marigold BESS SLF |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | 860 GIRVINSW |
| Point of interconnection | 860 GIRVINSW 345kV |
| County | Pecos |
| State | TX |
| Voltage | 345 kV |
| Capacity | 153.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-04-26 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
860 GIRVINSW substation: 3 requests in the ERCOT queue, 3 active totaling 317 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 29INR0263 | Whitethorn Solar Project | 163.1 | Solar | SS Completed, FIS Started, No IA |
| 26INR0715 | Tierra Bonita BESS SLF | 0 | Battery | SS Completed, FIS Started, No IA |
Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-09 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
Additional filed fields
| Interconnecting entity | Marigold BESS LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2026-10-03 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.