Substation Scout

Ashtrom Marigold BESS SLF

ERCOT queue ID 29INR0324

Ashtrom Marigold BESS SLF (29INR0324) is listed in the ERCOT interconnection queue as a 153.9 MW battery project in Pecos County, TX. The filing names 860 GIRVINSW as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 26, 2029. It records the screening study as complete on October 3, 2026.

Queue ID29INR0324
Project nameAshtrom Marigold BESS SLF
Status (as published)SS Completed, FIS Started, No IA
Substation860 GIRVINSW
Point of interconnection860 GIRVINSW 345kV
CountyPecos
StateTX
Voltage345 kV
Capacity153.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-04-26
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

860 GIRVINSW substation: 3 requests in the ERCOT queue, 3 active totaling 317 MW.

Queue IDProjectMWResourceStatus
29INR0263Whitethorn Solar Project163.1SolarSS Completed, FIS Started, No IA
26INR0715Tierra Bonita BESS SLF0BatterySS Completed, FIS Started, No IA

Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 Status change n/a SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting entityMarigold BESS LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Screening study complete2026-10-03

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first