Mentions: November 2024

Each row is one PJM document naming substations for one project, newest first. Atom feed

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

DateDocumentProjectSubstations namedAs printed
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Genoa-Westar Rebuild Genoa
Westar
Cost 8.789
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Genoa-Westar Sag Remediation Genoa
Westar
Cost 2.815
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Jester - Hayden Hayden
Jester New
Cost 229.411
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Maliszewski 765/345 kV Upgrades Bokes Creek
Corridor
Hyatt
Maliszewski
Marysiville
Marysville
West Millersport
Cost 145.494
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Maliszewski-Polaris Rebuild Maliszewski
Polaris
Cost 8.884
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Maliszewski Series Reactor Upgrades Maliszewski Cost 2.328
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
New 345 kV line between Bayshore to Davis Besse to Lake Ave Bay Shore
Bayshore
Davis Besse
Lake Ave
Lemoyne
Cost 257.3
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
New 345 kV line between Bayshore to Davis Besse to Lake Ave New 345 kV line between Lemoyne to Lake Ave Bay Shore
Bayshore
Davis Besse
Lake Ave
Lemoyne
Cost 344.1
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
New 345 kV line between Lemoyne - Lake Ave Lake Ave
Lemoyne
Cost 202.0
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
New 345 kV line between Lemoyne to Lake Ave Lake Ave
Lemoyne
Cost 455.0
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
New double circuit 345 kV line between Fostoria Central and Lake Ave Fostoria Central
Lake Ave
Cost 328.3
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
Rebuild/Reconductor existing 138 kV lines/Terminal upgrades at 345 kV substations Avery
Bayshore
Beaver
Davis Besse
Greenfield
Hayes
Johnson
Lakeview
Ottawa
Shinkrock
Cost 265.1
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 3
AEP Transmission Zone: Baseline B3295 Cancellation
B3295
Big Rock
Bull Creek
Grundy
Knotty Poplar
Patrick
Thomas
Status Cancellation (Cancelled)
Cost $0.8M
In service 6/1/2025
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 5
ComEd Transmission Zone: Baseline Change No Load Taps at 6 stations Crawford
Elmhurst
Fisk
Skokie
Taylor
West Loop
Cost $289 K
In service 4/15/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 8
AEP Transmission Zone: Baseline Cloverdale 138kV XT8 Circuit Switcher Replacement
b3897.1
Cloverdale Cost $1.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 10
AEP Transmission Zone: Baseline Sunnyside 138kV BB CB Replacement
b3882.1
Sunnyside Cost $1.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 12
AEP Transmission Zone: Baseline Greentown 138kV CS-XT5 Circuit Switcher Replacement
b3887.1
Greentown Cost $1.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 14
AEP Transmission Zone: Baseline Jacksons Ferry 138kV L Circuit Switcher Replacement
b3895.1
Jacksons Ferry Cost $1.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 16
AEP Transmission Zone: Baseline Hartford Transformer Tap Change Replacement
b3872.1
Hartford
Keelette
Sister Lakes
Cost $0.1M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 18
AEP Transmission Zone: Baseline Benwood 69kV A CB Replacement
b3886.1
Benwood Cost $1.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 20
AEP Transmission Zone: Baseline Van Wert 69kV D CB Replacement
b3884.1
Van Wert Cost $1.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 22
AEP Transmission Zone: Baseline Mount Vernon 69kV A and S CB Replacements
b3892.1
Mount Vernon Cost $2.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 24
AEP Transmission Zone: Baseline Schroyer Avenue 69kV M and N CB Replacements
b3885.1
Schroyer Avenue Cost $2.0M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 26
AEP Transmission Zone: Baseline Greenleaf Cap Bank
b3873.1
Conant
Greenleaf
Middlebury
Middleton Run
Parkway
Wyland
Cost $1.314M
In service 6/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 28
AEP Transmission Zone: Baseline Firebrick – Jefferson 69kV Reconductor
b3875.1
Firebrick
Jefferson
Lick
Cost $8.5M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 30
AEP Transmission Zone: Baseline Richlands Cap 69kV Bank Installation
b3876.1
Richlands
Town of Richlands
Cost $1.0M
In service 12/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 32
AEP Transmission Zone: Baseline Toronto – South Toronto Tap 69kV Reconductor
b3879.1
South Toronto
South Toronto Tap
Toronto
Cost $1.1M
In service 6/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 34
AEP Transmission Zone: Baseline Beatty 69kV Cap Bank
b3880.1
Ballah SS
Beatty
Beatty Road
Big Darby SS
Clark Lakes
Darbyville
Deer Creek
Dry Run SS
Galloway
Madison
Texas Eastern
Cost $2.25M
In service 6/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 36
AEP Transmission Zone: Baseline Haviland Station Upgrades
b3883.1
Cavett
Haviland
North Van Wert
Cost $0.8M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 38
AEP Transmission Zone: Baseline East Leipsic – AE2-072 (Lammer) Sag Study and Mitigation
b3888.1
East Leipsic
Lammer
Cost $2.5M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 40
AEP Transmission Zone: Baseline Tiltonsville Upgrades
b3889.1
Tiltonsville
Windsor
Windsor Junction
Cost $0.8M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 42
AEP Transmission Zone: Baseline South Coshocton Station Upgrades
b3890.1
Ohio Central
South Coshocton
Cost $0.2M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 44
AEP Transmission Zone: Baseline Kenny - Roberts 138kV Relay Upgrades
b3891.1
Kenny
Roberts
Cost $0.4M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 46
AEP Transmission Zone: Baseline Tidd Station Upgrades
b3894.1
Carnegie
Tidd
Cost $0.5M
In service 4/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 48
AEP Transmission Zone: Baseline Skimmer Cap Bank Settings Adjustments
b3896.1
Skimmer Cost $0.1M
In service 6/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 50
AEP Transmission Zone: Baseline Buchanan – Keen Mountain Upgrades
b3898.1
Buchanan
Keen Mountain
Cost $0.1M
In service 12/1/2025
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 52
APS Transmission Zone: Baseline 2024 RTEP Window 1
b3870
Federal St
Federal Street
Springdale
Cost $0.69 M
In service 06/01/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 54
DLCO Transmission Zone: Baseline 2024 RTEP Window 1
b3871
Brunot Island Cost $8.0 M
In service 12/31/2028
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 56
ComEd Transmission Zone: Baseline Kewanee 138kV L7411 (74 7411) CB Replacement
b3903.1
Kewanee Cost $1.101 M
In service 6/1/2026
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 58
ComEd Transmission Zone: Baseline Electric Junction to W541 Reconductor
b3901.1
Electric Junction
ESS W541
TSS 111 Electric Junction
W541
Cost $1.657 M
In service 6/1/2029
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 60
ComEd Transmission Zone: Baseline Kewanee Bus 1
b3900.1
Kewanee Cost $0.204 M
In service 4/15/2029
2024-11-15 SRRTEP Western
Item 02 - AMPT Supplemental Projects p. 3
Carriage, OH
AMPT 2024-2
Bellevue
Carriage
Herbert
Load 14 MW
2024-11-15 SRRTEP Western
Item 03 - ComEd Supplemental Projects p. 3
Customer in Aurora
ComEd-2024-022
None named Load 91 MW
2024-11-15 SRRTEP Western
Item 03 - ComEd Supplemental Projects p. 5
Customer in Aurora
ComEd-2024-002
Aurora
Electric Junction
Status Engineering
Cost $0M
In service 12/31/26
Load 130 MW
2024-11-15 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 3
Fisher Body, IN
AEP-2024-IM003
Fisher Body
Grant station
No figures printed
2024-11-15 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 4
Putnam County, WV
AEP-2024-AP005
Hurricane
Teays
No figures printed
2024-11-15 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 5
Ireland Road, IN
AEP-2024-IM017
Ireland Road In service 12/31/2028
2024-11-15 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 7
Franklin, OH
AEP-2024-OH033
Bexley
Drew station New
St. Clair
St. Clair Ave
Status Scoping (Conceptual)
Cost $10.793 M
In service 11/30/2026
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 3
Mitchell Plant Separation
APS-2024-073
Charleroi
Mitchell
Yukon
No figures printed
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 4
Glen Falls – Fairview 138 kV Line
APS-2024-088
Fairview
Glen Falls Substation
No figures printed
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 6
Gordonsville – Pratts 115 kV Line
APS-2024-092
Gordonsville
Pratts
No figures printed
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 7
Belmont – Long Reach 138 kV Line
APS-2024-093
Belmont
Long Reach
No figures printed
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 9
Oak Mound Control Building and Breakers
APS-2024-095
Glen Falls Substation
Oak Mound Substation
Quiet Dell Substation
Rider
Waldo Run
No figures printed
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 11
Junction – Parr Run 138 kV Line
APS-2024-096
Junction Substation
Parr Run
No figures printed
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 13
Stony Springs Junction Area
APS-2023-022
Delmont Substation
Harrison City Substation
Hempfield
Luxor
North Greensburg Substation
North Oakford
Penn
Stony Springs Junction
Status Conceptual
Cost $13.6M
In service 6/22/2027
Load ~25 MW
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3
The Reybold 138/69 kV transformer
b3865.1
Delaware City
Reybold Substation
Cost $9.48 M
In service 12/31/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 4
Yorkana and Windsor area
b3858.1
Glades Substation
Windsor Substation
Yorkana 230 kV substation
Cost $33.1 M
In service 6/1/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 6
The Schuylkill 230/69 kV transformer
b3863.1
Schuylkill Substation Cost $0.1 M
In service 12/31/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 7
Richmond - Tacony 69 kV
b3864.1
Richmond
Tacony
Cost $0.350 M
In service 6/1/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 8
Penhorn to Union City 69 kV
b3868.1
Carlstadt
Kingsland 69kV Switch
Penhorn
River Road
Tonnelle
Union City
Cost $46 M
In service 6/1/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 9
Bergen 138 kV series reactors
b3869.1
Bergen
East Rutherford
Fairlawn
Cost $12.5 M
In service 9/1/2027
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 11
Chester 34.5kV Breaker
b3860.1
Chester Substation Cost $0.541M
In service 12/31/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 12
Werner 34.5kV Breaker
b3861.1
Werner Substation Cost $0.541M
In service 12/31/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 02 - UGI Supplemental Projects p. 3
UGI Transmission Zone: Supplemental Project
UGI-2023-0001
Hanover
Palooka
Plymouth
Status Engineering
Cost $20M
In service October 2026
2024-11-14 SRRTEP Mid-Atlantic
Item 03 - PPL Supplemental Projects p. 3
Lofty, PA
PPL-2024-0018
None named In service 3/31/2026
Load 45MW
2024-11-14 SRRTEP Mid-Atlantic
Item 03 - PPL Supplemental Projects p. 4
Beltway, PA
PPL-2024-0019
None named In service 5/31/2026
Load 50MW
2024-11-14 SRRTEP Mid-Atlantic
Item 03 - PPL Supplemental Projects p. 6
Middleburg, PA
PPL-2019-0003
Beavertown
Middleburg
Sunbury
Cost $33 M
In service 05/31/2028
2024-11-14 SRRTEP Mid-Atlantic
Item 04 - MetEd Supplemental Projects p. 3
Frystown – South Lebanon 69 kV Line
ME-2024-022
Frystown
South Lebanon
No figures printed
2024-11-14 SRRTEP Mid-Atlantic
Item 04 - MetEd Supplemental Projects p. 4
Muhlenberg – North Temple 69 kV Line
ME-2024-023
Muhlenberg Substation
North Temple
Rosedale
No figures printed
2024-11-14 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 3
Cooper and Prospect Substation Terminal Upgrades
PN-2024-032
Cooper Substation
Prospect Substation
No figures printed
2024-11-14 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 4
East Pike – Glory 115 kV Line
PN-2024-027
East Pike
Glory
No figures printed
2024-11-14 SRRTEP Mid-Atlantic
Item 05 - PENELEC Supplemental Projects p. 5
Blairsville East – Shelocta 115 kV Line
PN-2024-029
Blairsville East
Shelocta
No figures printed
2024-11-14 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 3
Oceanview – Bradley Beach 34.5 kV D130 Line Customer Connection
JCPL-2024-046
Bradley Beach
Oceanview
In service 07/03/2026
Load approximately 8.5 MVA
2024-11-14 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 5
Vernon No. 4 115-34.5 kV Transformer
JCPL-2024-025
Vernon Status Engineering
Cost $7M
In service 8/31/2029
2024-11-14 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 7
Deep Run No. 2 115-34.5 kV Transformer
JCPL-2024-026
Deep Run Substation Status Conceptual
Cost $8M
In service 12/31/2027
2024-11-14 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 9
Gilbert No. 2 and No. 3 115-34.5-13.2 kV Transformers
JCPL-2024-027
Gilbert Status Conceptual
Cost $8M
In service 12/31/2028
2024-11-14 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects p. 11
Englishtown No. 1 115-34.5 kV Transformer
JCPL-2024-028
Englishtown Status Conceptual
Cost $7M
In service 12/31/2027
2024-11-14 SRRTEP Southern
Item 01 - SRRTEP South - Reliability Analysis Update p. 3
DOM Transmission Zone: Baseline Merck #5 to Port Republic 115kV Merck #5 substation
Port Republic Substation
Cost $42.3M
In service 6/1/2029
2024-11-14 SRRTEP Southern
Item 01 - SRRTEP South - Reliability Analysis Update p. 5
DOM Transmission Zone: Baseline Bremo 138/115kV Transformer #8 None named Cost $.092M
In service 6/1/2029
2024-11-14 SRRTEP Southern
Item 01 - SRRTEP South - Reliability Analysis Update p. 7
DOM Transmission Zone: Baseline Alta Vista 138/115kV Transformer #3 None named Cost $5M
In service 6/1/2029
2024-11-14 SRRTEP Southern
Item 01 - SRRTEP South - Reliability Analysis Update p. 9
DOM Transmission Zone: Baseline Line #1031 Pantego to Terra 115kV None named Cost $26.6M
In service 6/1/2029
2024-11-06 TEAC
Item 04 - APS Supplemental Projects p. 3
Wylie Ridge No. 3 345/138 kV Transformer
APS-2024-079
Wylie Ridge Substation No figures printed
2024-11-06 TEAC
Item 04 - APS Supplemental Projects p. 4
Wylie Ridge No. 7 500/345 kV Transformer
APS-2024-080
Wylie Ridge Substation No figures printed
2024-11-06 TEAC
Item 04 - APS Supplemental Projects p. 5
Lime Kiln – Montgomery 230 kV Line
APS-2024-091
Lime Kiln
Montgomery
No figures printed
2024-11-06 TEAC
Item 04 - APS Supplemental Projects p. 7
Monocacy No. 4 230/138 kV Transformer
APS-2024-061
Monocacy Substation Status Engineering
Cost $9.00 M
In service 12/31/2027
2024-11-06 TEAC
Item 05 - JCPL Supplemental Projects p. 3
Morris Park Substation
JCPL-2023-011
Gilbert
Martins Creek
Morris Park
Pequest River
Status Conceptual
Cost $15.4M
In service 1/29/2027
Load 13 MW
2024-11-06 TEAC
Item 06 - MetEd Supplemental Projects p. 3
North Hershey Substation
ME-2023-022
North Hershey Status Conceptual
Cost $16.31M
In service 12/17/2027
2024-11-06 TEAC
Item 07 - AEP Supplemental Projects p. 3
Fort Wayne, IN
AEP-2024-IM014
Allen
East Lima
RP Mone
Sorenson
No figures printed
2024-11-06 TEAC
Item 07 - AEP Supplemental Projects p. 5
New Carlisle, IN
AEP-2024-IM016
None named Load 437MW
2024-11-06 TEAC
Item 07 - AEP Supplemental Projects p. 7
New Haven, Indiana
AEP-2023-IM026
Allen
Robison Park
Zodiac New
Status Scoping (Conceptual)
Cost $169.1 M
In service 07/01/2029
Load 1200MW
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 3
New Buffalo, PA
PPL-2024-0017
None named In service 05/2027
Load 1,000 MW
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 5
Lancaster, PA
PPL-2024-0010
Engleside
Greenland
Lampeter New
Millwood
Pitney New
Prince
South Akron
Strasburg
Status Conceptual
Cost $117.8 M
In service 06/01/2028
Load 350 MW
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 7
Lancaster, PA
PPL-2024-0011
Dillerville
North Lancaster New
Prince
South Akron
West Hempfield
Status Conceptual
Cost $67.5 M
In service 06/01/2028
Load 350 MW
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 9
Hazleton, PA
PPL-2024-0012
Harwood
Slykerville New
Susquehanna
Tresckow
Status Conceptual
Cost $73.3 M
In service 05/30/2028
Load 1,000 MW
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 11
Alburtis, PA
PPL-2024-0013
Alburtis Status Conceptual
Cost $19.9 M
In service 12/31/2026
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 13
Wescosville, PA
PPL-2024-0014
Wescosville Status Conceptual
Cost $15.5 M
In service 12/31/2026
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 15
Lackawanna, PA
PPL-2024-0015
Lackawanna Status Conceptual
Cost $6.3 M
In service 12/31/2026
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 17
New Buffalo, PA
PPL-2024-0016
Blooming Grove Status Conceptual
Cost $6.3 M
In service 12/31/2027
2024-11-06 TEAC
Item 09 - PECO Supplemental Projects p. 3
PE-2024-007 None named No figures printed
2024-11-06 TEAC
Item 09 - PECO Supplemental Projects p. 4
New Business Customer
PE-2024-008
None named Load 600MW
2024-11-06 TEAC
Item 10 - PEPCO Supplemental Projects p. 3
Mt. Zion
PEP-2024-003
Mt. Zion Substation No figures printed
2024-11-06 TEAC
Item 11 - ComEd Supplemental Projects p. 3
Burnham 345kV BT1-2 CB
ComEd-2024-018
Burnham
Sheffield
Status Engineering
Cost $2.1M
In service 12/31/24
2024-11-06 TEAC
Item 11 - ComEd Supplemental Projects p. 5
Burnham 345kV BT2-13 CB
ComEd-2024-019
Bloom
Burnham
Status Engineering
Cost $2.1M
In service 12/31/25
2024-11-06 TEAC
Item 11 - ComEd Supplemental Projects p. 7
Burnham 345kV BT12-13 CB
ComEd-2024-020
Burnham
Davis Creek
State Line
Status Engineering
Cost $2.1M
In service 12/31/26
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0075
Ocean Court In service 10/1/2028
Load 300 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 4
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0076
Global Plaza In service 1/1/2027
Load 295 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 5
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0077
Prentice Drive In service 2/28/2026
Load 247.2 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 6
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0078
Export New In service 1/1/2028
Load in excess of 100 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 7
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0079
Executive New In service 2/1/2028
Load in excess of 100 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 8
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0080
Rock Bottom New In service 3/31/2029
Load in excess of 100 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 9
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0081
Meteor New In service 1/1/2027
Load 239 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 10
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0082
Chandler Sub New In service 10/15/2027
Load 112 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 11
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0083
McDevitt New In service 10/15/2027
Load 118 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 12
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0084
Mt. Pony Sub New In service 01/01/2027
Load 160 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 13
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0085
Palomino Sub New In service 07/01/2028
Load 120 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 15
Dominion Transmission Zone: Supplemental Park Center 230kV Delivery - DEV
DOM-2020-0043- UPDATE
Dulles
Lincoln Park
Park Center New
Reston
Status Engineering
Cost $27.0 M
In service 11/21/2025
Load 41.0 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 17
Dominion Transmission Zone: Supplemental Towerview 230kV Delivery - DEV
DOM-2023-0004
Park Center
Reston
Towerview New
Status Engineering
Cost $13.0 M
In service 11/30/2027
Load 300.0 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 19
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency
DOM-2022-0058
Churchland
Navy North
Navy South
Sewells Point
Status Cancelled
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 20
Dominion Transmission Zone: Supplemental NIT Substation 230kV Delivery - DEV
DOM-2023-0006
Churchland
NIT New
Sewells Point
Status Construction (Under construction)
Cost $5.7 M
In service 12/31/2024
Load 49.3 MW
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 22
Dominion Transmission Zone: Supplemental Do No Harm Analysis
DOM-2023-0006-DNH
Navy North
NIT
Sewells Point
South
Status Engineering
Cost $3 M
In service 3/31/2026
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 24
Dominion Transmission Zone: Supplemental Lost City 230kV Delivery - DEV
DOM-2024-0041
Lost City Status Engineering
Cost $0.5M
In service 06/01/2026
Load 187.0 MW
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 18
Conastone 230 kV 2322 B5 CB Replacement
b3857
Conastone Cost $1.921M
In service 6/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 21
Beatty – Adkins 345kV Station Upgrades Adkins
Beatty
Chenoweth
Cost $5M
In service 4/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 23
Canal – Gay St. 138kV Rebuild
2024-W1-940
Canal
Gay
Cost $15.595 M
In service 12/31/2027
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 25
Cluster AEP-2
2024-W1-856
Bixby
Buckeye Steel
Canal
Marion Road
Mound St
Cost $31.090 M
In service 12/31/2028
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 28
Cluster AEP-6
2024-W1-769
Beatty Road
Cyprus
McComb
White Road
Cost $33.113 M
In service 4/30/2028
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 31
Wilton Center BT 4-5 CB Wilton Center Cost $2.7 M
In service 12/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 33
Cluster 1
2024-W1-135
Dresden
Mulberry
Pontiac
Cost $16.27 M
In service 6/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 36
Cluster 2
ComEd-2024-004
Busse
Des Plaines
Itasca
Cost $14.31 M
In service 6/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 39
Delco Tap – Mickleton Facility Upgrades Delco Tap
Mickleton
Cost $1.03M
In service 06/01/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 40
Milford and Cedar Creek Facility Upgrades Cedar Creek
Milford
Cost $0.200M
In service 12/31/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 41
Elroy – Hosensack Facility Upgrades Elroy
Hosensack
Cost $1.5M
In service 06/01/2029:
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 42
BGE Local N-1-1 Chestnut Hill
Frederick Rd.
Graceton
Howard
Marley Neck New
North East
Pumphrey
Wagner
No figures printed
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 45
PECO Transmission Zone: Baseline
2024-W1-12
Eagle Point
Master
North Philadelphia
Penrose
Richmond
Waneeta
Cost $43.22 M
In service 6/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 48
Pocono area Evaluation Progress Acahela
Jenkins
Lackawanna
Pocono
Siegfried
Cost $4.93
In service 10/30/2027
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 50
PPL Transmission Zone: Baseline
2024-W1-935
Cumberland
Glen Brook
Glenbrook
Hunterstown
Juniata
Susquehanna
Susquehanna T10
Three Mile Island
Williams Grove
In service 6/1/2029
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 54
Clusters AEP- 3, 4, 5 (Shortlist) Genoa
Hayden
Hyatt
Jester New
Maliszewski
Marysville
Polaris
Vassell
West Millersport
Westar
No figures printed
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 57
Cluster 2 (ATSI) Avery
Bay Shore
Bayshore
Beaver
Davis Besse
Fostoria Central
Greenfield
Hayes
Johnson
Lake Ave
Lake Avenue
Lakeview
Lemoyne
Ottawa
Shinkrock
No figures printed

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

Before relying on any of this