Substation Scout

Navy South

Named in 1 PJM planning document for 1 project, on November 6, 2024.

Not stateddescribed as
DOMzone
230kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency
DOM-2022-0058
Cancelled Not printed Not printed Not printed 2024-11-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 19
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency No role wording
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this