Burnham
Named in 7 PJM planning documents for 5 projects, from November 6, 2024 to October 16, 2026.
PJM interconnection queue
A PJM queue substation page has the same name: Burnham (IL) — 2 queue requests filed, 2 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Burnham 345kV BT1-2 CB ComEd-2024-018 · s3585.1 |
In service | $2.1M | 12/31/24 | Not printed | 2025-10-08 TEAC |
| Burnham 345kV BT2-13 CB ComEd-2024-019 · s3586.1 |
Engineering | $2.1M | 12/31/25 | Not printed | 2025-10-08 TEAC |
| Burnham 345kV BT12-13 CB ComEd-2024-020 · s3587.1 |
Engineering | $2.1M | 12/31/26 | Not printed | 2025-10-08 TEAC |
| Burnham 345KV/138KV TR ComEd-2026-009 |
Engineering | Not printed | Phase 1: 12/31/2026, Phase 2: 12/31/2028 | Not printed | 2026-07-07 TEAC |
| Burnham ComEd-2026-017 |
Under construction | $1.4 M | 11/13/26 | Not printed | 2026-10-16 SRRTEP Western |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Status | engineering (Engineering) → in-service (In Service) | 2024-11-06 | 2025-10-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-16 | SRRTEP Western Item 04 - ComEd Supplemental Projects Presentation p. 9 |
Burnham | “Upgrade Burnham 138KV Bus 1-2, BT 2-3, Bus 3 and BT 3-4 Relays” 138KV |
| 2026-09-18 | SRRTEP Western Item 04 - ComEd Supplemental Projects p. 7 |
Burnham | “Burnham 138KV Bus 1-2, BT 2-3, Bus 3 and BT 3-4 electromechanical relays are obsolete and are being phased out of the system.” 138KV |
| 2026-09-08* | SRRTEP Western ComEd local plan submission of the supplemental projects for 2025 RTEP p. 18 |
Burnham 345kV BT1-2 CB | “Burnham 345kV BT1-2 oil circuit breaker was installed in 1971” 345kV |
| 2026-09-08* | SRRTEP Western ComEd local plan submission of the supplemental projects for 2025 RTEP p. 20 |
Burnham 345kV BT2-13 CB | “Burnham 345kV BT2-13 oil circuit breaker was installed in 1971” 345kV |
| 2026-09-08* | SRRTEP Western ComEd local plan submission of the supplemental projects for 2025 RTEP p. 22 |
Burnham 345kV BT12-13 CB | “Burnham 345kV BT12-13 oil circuit breaker was installed in 1988” 345kV |
| 2026-07-07 | TEAC Item 12 - ComEd Supplemental Projects p. 6 |
Burnham 345KV/138KV TR | “Burnham autotransformer 345KV/138KV TR84 300MVA was installed in 1974” 345KV/138KV |
| 2026-06-02 | TEAC Item 10 - ComEd Supplemental Projects p. 3 |
Burnham 345KV/138KV TR | “Burnham autotransformer 345KV/138KV TR84 300MVA was installed in 1974. It is deteriorating condition” 345KV/138KV |
| 2025-10-08 | TEAC Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 18 |
Burnham 345kV BT1-2 CB | “Burnham 345kV BT1-2 oil circuit breaker was installed in 1971” 345kV |
| 2025-10-08 | TEAC Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 20 |
Burnham 345kV BT2-13 CB | “Burnham 345kV BT2-13 oil circuit breaker was installed in 1971” 345kV |
| 2025-10-08 | TEAC Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 22 |
Burnham 345kV BT12-13 CB | “Burnham 345kV BT12-13 oil circuit breaker was installed in 1988” 345kV |
| 2024-11-06 | TEAC Item 11 - ComEd Supplemental Projects p. 3 |
Burnham 345kV BT1-2 CB | “Burnham 345kV BT1-2 oil circuit breaker was installed in 1971” 345kV |
| 2024-11-06 | TEAC Item 11 - ComEd Supplemental Projects p. 5 |
Burnham 345kV BT2-13 CB | “Burnham 345kV BT2-13 oil circuit breaker was installed in 1971” 345kV |
| 2024-11-06 | TEAC Item 11 - ComEd Supplemental Projects p. 7 |
Burnham 345kV BT12-13 CB | “Burnham 345kV BT12-13 oil circuit breaker was installed in 1988” 345kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.