Substation Scout

Mentions: December 2025

Each row is one PJM document naming substations for one project, newest first. Atom feed

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

DateDocumentProjectSubstations namedAs printed
2025-12-12 SRRTEP Western
Item 12 - DEOK Supplemental Projects p. 3
New Customer Load Request
DEOK-2025-006
None named Load 240 MW
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 3
Collins Park – Ryan 69 kV
ATSI-2025-037
Collins Park West
Ryan Substation
No figures printed
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 4
Rockaway Substation 69 kV
ATSI-2025-038
OS Kelly
Rockaway Substation
Springfield Medical
No figures printed
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 5
Chrysler Substation 138 kV
ATSI-2025-039
Chrysler Substation
First Solar
Shelby
No figures printed
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 7
Newton Falls 138/69 kV Substation
ATSI-2022-031
Bridge
Evergreen Substation
Franklin
GM Lordstown
Hanna
Ivanhoe
Newton Falls
Newton Falls 138/69 kV Substation
Ohio Star Forge
Whitman Station New
Status Conceptual
Cost $51.52M
In service 12/21/2028
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 9
Multiple Line Rehab/Rebuild
ATSI-2019-059
Department of Corrections
Dept. of Corrections
McDowell
Mercer
Mercer Forge
Mercer Tap
Reznor Tap
Reznor Thomas
Sharon
Status Conceptual
Cost $63.7M
In service 12/31/2030
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 11
New Customer Connection
ATSI-2025-033
London
Tangy
Status Conceptual
Cost $3.72M
In service 06/01/2027
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 13
New Customer Connection
ATSI-2025-034
Nottingham
Yager Substation
Status Conceptual
Cost $2.32M
In service 04/19/2029
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 15
New Wholesale Connection
ATSI-2025-030
Clark
North Hampton Substation
Status Conceptual
Cost $2.25M
In service 06/01/2028
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 17
Black River - Willow Creek 69 kV
ATSI-2025-035
Black River
Willow Creek
Status Conceptual
Cost $1.53M
In service 12/31/2026
2025-12-12 SRRTEP Western
Item 14 - APS Supplemental Projects p. 3
Grand Point – Roxbury 138 kV
APS-2024-028
Grand Point
Greene Substation
Letterkenny Substation
Roxbury Substation
Status Conceptual
Cost $28.34M
In service 06/15/2029
2025-12-12 SRRTEP Western
Item 14 - APS Supplemental Projects p. 6
Junction – Parr Run 138 kV
APS-2024-096
Junction Substation
Kelso Gap
Parr Run
Status Conceptual
Cost $35M
In service 06/16/2028
2025-12-12 SRRTEP Western
Item 14 - APS Supplemental Projects p. 9
Page-Riverton 138 kV New Customer
APS-2023-014 · s3127.1
Catlett Mountain New
Page
Riverton
Status Project Initiation (Cancelled)
Cost $16M
In service 05/30/2025
2025-12-12 SRRTEP Western
Item 15 - AEP Supplemental Projects p. 3
Jennings Road Switch, OH/Sharp Road, OH/Commerce, OH
AEP-2024-OH028
Commerce
Jennings Road Switch
Sharp Rd
Sharp Road
Status Scoping (Conceptual)
Cost $2.575 M
In service 08/04/2027
Load 12.031 MW
2025-12-12 SRRTEP Western
Item 16 - SRRTEP West - Reliability Analysis Update p. 3
Mendota-Sandwich 138 kV
b4025.1
Haumesser
Mendota
Sandwich
Steward
Waterman
Cost $171.88 M
In service 4/15/2030
2025-12-12 SRRTEP Western
Item 16 - SRRTEP West - Reliability Analysis Update p. 5
Mound Street-St Clair Avenue 138kV Line Rebuild
b4028.1
Mound Street
Saint Clair
St Clair Avenue
Cost $41.586M
In service 04/01/2030
2025-12-12 SRRTEP Western
Item 16 - SRRTEP West - Reliability Analysis Update p. 8
b4000.209 Cancellation
b4000.209
Altavista
Otter
Status Cancelled
Cost $1.2 M
In service 6/1/2029
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 3
Montville, NJ/Riverdale Substation, NJ
JCPL-2025-007
Montville
Riverdale
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 4
Allenhurst Substation, NJ
JCPL-2025-008
Allenhurst Substation
Oceanview
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 5
New Providence Substation, NJ
JCPL-2025-009
Air Reduction
CSC H Tap
New Providence
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 6
Morris Court Substation, NJ
JCPL-2025-011
Morris Court Substation In service 9/14/2026
Load 10 MW
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 7
Manitou, NJ
JCPL-2025-012
Manitou
Ocean Beach
Ortley Beach
Seaside Park
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 9
Martinsville, NJ
JCPL-2025-010
Martinsville
Readington
Status Conceptual
Cost $1.08M
In service 06/01/2027
Load 10 MW
2025-12-11 SRRTEP Mid-Atlantic
Item 09 - MetEd Supplemental Projects p. 3
Fairview, NJ
ME-2025-003
Fairview
Gitts Run
Load 41 MW
2025-12-11 SRRTEP Mid-Atlantic
Item 09 - MetEd Supplemental Projects p. 5
Carpenter Technology Substation 69kV Circuit Breaker
ME-2024-021
Carpenter Technology Substation
Riverview
Status Conceptual
Cost $1.01M
In service 06/15/2027
2025-12-11 SRRTEP Mid-Atlantic
Item 09 - MetEd Supplemental Projects p. 7
Cleona – Campbelltown 69kV Line
ME-2023-009
Annville
Campbelltown Substation
Cleona
Hershey Beta Tap
Middletown Jct.
Mill St.
Millards Quarry
N. Hershey
North Lebanon
Status Conceptual
Cost $32.33M
In service 06/01/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 10 - PENELEC Supplemental Projects p. 3
Bethlehem, PA
PN-2025-009
Bethlehem
Ebensburg
Nanty Glo
Revloc
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 10 - PENELEC Supplemental Projects p. 5
Grand Point – Roxbury 138kV Line
PN-2024-012
Grand Point
Greene
Letterkenny
Roxbury
Status Conceptual
Cost $17.94M
In service 06/15/2029
2025-12-11 SRRTEP Mid-Atlantic
Item 10 - PENELEC Supplemental Projects p. 7
Glory – Nanty Glo – Spangler 46 kV Line
PN-2024-022
Bobik Lane New
Glory
Moss Creek
Nanty Glo
Nicktown
Spangler
Strongstown
Teakettle
Status Conceptual
Cost $13.81M
In service 06/30/2028
Load 11 MW
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 3
Shillington, PA
PPL-2023-0001
Shillington Substation No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 4
White Haven, PA
PPL-2025-0026
White Haven In service 12/2026
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 5
Bear Creek, PA
PPL-2025-0027
Bear Creek In service 11/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 6
Fountain Springs, PA
PPL-2025-0028
Fountain Springs In service 11/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 7
Parrish, PA
PPL-2025-0029
Parrish In service 11/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 8
Mausdale, PA
PPL-2025-0030
Mausdale New In service 3/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 10
Allentown, PA
PPL-2022-0006
Sumner Status Conceptual
Cost $24.6M
In service 12/1/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 13
Derry, PA
PPL-2025-0020
Derry
Washingtonville New
Status Conceptual
Cost $1.25 M
In service 05/30/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 15
Hughesville, PA
PPL-2025-0021
Hughesville Status Conceptual
In service 01/30/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 17
Coopersburg, PA
PPL-2025-0022
Center Valley New
Coopersburg
Status Conceptual
Cost $1.85 M
In service 11/30/2027
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 19
West Damascus, PA
PPL-2025-0025
West Damascus Status Engineering
Cost $0.5 M
In service 05/26/2027
2025-12-11 SRRTEP Mid-Atlantic
Item 12 - PSEG Supplemental Projects p. 3
PSE&G Central Territory
PSEG-2025-0008
Brunswick
Harts Lane
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 12 - PSEG Supplemental Projects p. 4
PSE&G Southern Territory
PSEG-2025-0009
Lawrence No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 12 - PSEG Supplemental Projects p. 5
PSE&G Southern Territory
PSEG-2025-0010
Lawnside
Nicholson
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 12 - PSEG Supplemental Projects p. 7
PSE&G Central Territory
PSEG-2025-0006
Sand Hills Status Conceptual
Cost $25.1M
In service 12/31/2027
2025-12-11 SRRTEP Mid-Atlantic
Item 12 - PSEG Supplemental Projects p. 9
PSE&G Southern Territory
PSEG-2025-0007
Gloucester
Lawnside
Status Conceptual
Cost $42.8M
In service 12/31/2028
2025-12-11 SRRTEP Mid-Atlantic
Item 13 - DPL Supplemental Projects p. 3
DPL-2025-003 Carrcroft
Edgemoor
Silverside
No figures printed
2025-12-11 SRRTEP Mid-Atlantic
Item 14 - ACE Supplemental Projects p. 3
ACE-2025-001 Beckett
Churchtown
Status Engineering
Cost $16M
In service Phase 1 – 4/28/2026, Phase 2 – 12/2029
Load 40 MW
2025-12-11 SRRTEP Mid-Atlantic
Item 15 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3
ODEC Transmission Zone b3134 Cost Update
b3134
Cheriton S/S New
Kellam
Kellam S/S
Status EP
Cost $43.4M
In service 12/31/2027
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 3
Equipment Material Condition, Performance and Risk
DOM-2025-0085
Central Substation In service 12/31/2029
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 4
Customer Load Request
DOM-2025-0090
Glasgow substation In service 05/01/2027
Load 25 MW
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 5
Customer Load Request
DOM-2025-0093
Craigsville Substation In service 12/31/2029
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 6
Customer Load Request
DOM-2025-0097
None named In service 10/31/2027
Load 20.1 MW
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 8
Jarratt 115kV Delivery – Upgrade TX#4 and Retire TX#3 - DEV
DOM-2025-0076
Jarratt Substation Status Engineering
Cost $0.4M
In service 6/30/2028
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 10
Harmony Village 115 kV Delivery – Upgrade TX#3 - DEV
DOM-2025-0077
Harmony Village Substation Status Engineering
Cost $1.21M
In service 12/15/2026
2025-12-11 SRRTEP Southern
Item 03 - SRRTEP South - Reliability Analysis Update p. 3
DOM Transmission Zone: Baseline Bremo to Fork Union 115kV
b4031.1
Bremo
Fork Union
Cost $7M
In service 6/1/2030
2025-12-08 TEAC
Item 04 - ATSI Supplemental Projects p. 3
Lemoyne Substation Upgrades for MISO Tranche 2.1
ATSI-2025-004
Greenfield
Lakeview
Lemoyne
Ottawa
Status Conceptual
Cost $100.86 M
In service 6/1/2032
2025-12-08 TEAC
Item 04 - ATSI Supplemental Projects p. 6
Lallendorf Substation Upgrades for MISO Tranche 2.1
ATSI-2025-005
Allen Junction Substation
Lallendorf Substation
Morocco
Status Conceptual
Cost $7.21 M
In service 6/1/2032
2025-12-08 TEAC
Item 05 - APS Supplemental Projects p. 3
Yukon No. 7 500/138 kV Transformer
APS-2025-030
Yukon No figures printed
2025-12-08 TEAC
Item 05 - APS Supplemental Projects p. 5
Elko No. 1 230/138 kV Transformer
APS-2025-012
Elko Substation Status Conceptual
Cost $6.69M
In service 06/01/2028
2025-12-08 TEAC
Item 06 - JCPL Supplemental Projects p. 3
Glen Gardner No. 1 230-34.5 kV Transformer
JCPL-2024-022
Glen Gardner Status Conceptual
Cost $ 7.35M
In service 11/17/2028
2025-12-08 TEAC
Item 06 - JCPL Supplemental Projects p. 5
Glen Gardner No. 8 230-34.5 kV Transformer
JCPL-2024-031
Glen Gardner Status Conceptual
Cost $ 7.35M
In service 06/07/2028
2025-12-08 TEAC
Item 06 - JCPL Supplemental Projects p. 7
Englishtown No. 6 230-34.5 kV Transformer
JCPL-2025-005
Englishtown Status Conceptual
Cost $ 2.06M
In service 12/17/2026
2025-12-08 TEAC
Item 07 - PEPCO Supplemental Projects p. 3
Burches Hill
PEP-2023-023
Burches Hill Status Engineering
Cost $3.6M
In service 2/12/2027
2025-12-08 TEAC
Item 08 - BGE Supplemental Projects p. 3
BGE-2025-011 None named Load 880 MW
2025-12-08 TEAC
Item 09 - ComEd Supplemental Projects p. 3
Zion 345 kV CBs
ComEd-2025-024
Pleasant Prairie
Waukegan
Zion
Status Conceptual
Cost $ 12.7 M
In service 12/31/2027
2025-12-08 TEAC
Item 09 - ComEd Supplemental Projects p. 5
State Line 345 kV CBs
ComEd-2025-025
State Line Status Conceptual
Cost $4M
In service 12/31/2026
2025-12-08 TEAC
Item 09 - ComEd Supplemental Projects p. 7
Des Plaines 345 kV CBs
ComEd-2025-026
Des Plaines
Itasca
Status Conceptual
Cost $3.9M
In service 12/31/2027
2025-12-08 TEAC
Item 10 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2025-0083
Cosner New In service 12/01/2027
Load 300 MW
2025-12-08 TEAC
Item 10 - DOM Supplemental Projects p. 5
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV
DOM-2025-0011
Hibie St New
Reeves Ave
Thrasher
Status Engineering
Cost $3.56M
In service 12/31/2027
Load 29.8 MW
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 13
AEP Transmission Zone: Baseline Cluster AEP-1
b4026.1
Auglaize
Platter Creek
Sherwood
Cost $28.7M
In service 2/28/2030
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 16
AEP Transmission Zone: Baseline Cluster AEP-5
b4027.1
Moneta
Rockcastle
Smith Mountain
Cost $9.879M
In service 06/01/2029
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 19
Dominion Transmission Zone: Baseline Hopewell – Chesterfield – Basin 230 kV
b4030.1
Basin
Chesterfield
Hopewell
Cost $113.55 M
In service 6/1/2030
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 21
Dominion Transmission Zone: Baseline 500kV Line #565 Rebuild (End of Life Criteria)
b4030.6
Septa
Suffolk
Yadkin
Cost $74.3 M
In service 6/1/2030
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 23
Dominion Transmission Zone: Baseline Charlottesville – Fork Union – Bremo 230 kV
b4030.9
Bremo
Charlottesville
Fork Union
Mt. Eagle Tap
Cost $127.05 M
In service 6/1/2030
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 27
PPL Transmission Zone: Baseline MAAC PPL Cluster
b4029.1
Glen Brook
Jenkins
Juniata
Kelayres New
Monroe
Montour
Sunbury
Susquehanna
Susquehanna T10
Tomhicken
Cost $565.4M
In service 6/1/2030
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 51
MAAC Regional Cluster: Baseline
2025-W1-237
Belmont
Buttermilk Falls
Conemaugh
Juniata
Kammer
Keystone
Mountain Stone New
Mountaineer
South Bend
Sunbury
Cost $1738.6M
In service 6/1/2031
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 59
PEPCO Transmission Zone: Baseline Exelon/PEPCO Cluster
2025-W1-919
Bells Mill
Brighton
Dickerson New
Quince Orchard
Cost $282.16 M
In service 6/1/2031
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 73
Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio
2025-W1-275
Carson
Chickahominy
Cunningham
Elmont
Heritage New
Kraken New
Midlothian
Mosby
North Anna
Possum Point
Surry
Vint Hill
Vontay New
Yeat
In service 6/1/2032
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 111
West Regional Cluster Solution - Transource/FE Proposal 2025-W1-570 (Modified)
2025-W1-570
Adkins New
Allen
Beatty
Bethel
Bixby
Cole
Conesville
Fifth Avenue
Greentown
Guernsey
Hayden
Hess
Hyatt
Kenny
Kirk
Maliszewski
Marysville
Meadow Lake
Newark Center
Ohio Central
OSU
Roberts
South Kenton
Teddy New
West Millersport New
Wilson
In service 10/31/2031
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 119
2025W1 – Regional Cluster Preferred Solution: Breaker Upgrades Celestial Sub
Clifton Sub
Elmont
Huntington Court
Susquehanna
Cost $18.5 M
In service 6/1/2030
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 130
Dominion Transmission Zone: Baseline New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line
b3800.210
Golden
Lockridge
Mars
Prentice Drive
Sojourner
Cost $431.62M
In service 6/1/2027
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 138
ACE/APS/ATSI/BGE/DPL/JCPL/ME/PECO/PENELEC/ComEd P5 CAPs: Baseline
b4075
None named Cost $35.759M
In service 7/1/2029

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

Before relying on any of this