Substation Expansion Tracker: PJM

Every substation named in PJM's transmission planning materials, and what each document says about it.

Why this exists

The substation dataset behind the Site Scanner is a snapshot. It tells you a substation exists, roughly where, and sometimes its maximum voltage. It cannot tell you that a utility has already presented a plan to rebuild it, or that a new substation is being proposed nearby.

That information is public. It sits in the materials PJM's Transmission Expansion Advisory Committee and its three Sub-Regional RTEP committees publish for every meeting: hundreds of pages of slides and tables, on a rolling basis. This tracker reads them and keeps a record of every substation they name.

3,457substations named
387described as new
670PJM documents read
2026-12-01latest document

Find a substation

Loading…

SubstationZoneDescribed askV as printedProjectsMentionsLast mentioned

By zone: AEP (687) · DOM (447) · ATSI (364) · APS (290) · JCPL (251) · PPL (186) · PJM system-wide (180) · COMED (138) · EKPC (136) · PENELEC (126) · METED (108) · DAYTON (85) · PSEG (84) · AMPT (80) · DEOK (79) · PECO (58) · BGE (37) · DPL (34) · ACE (23) · PEPCO (21) · DLCO (12) · WVPA (12) · UGI (10) · Zone not identified (7) · OVEC (2)

Latest mentions

The newest documents first. Full feed → · Atom feed

DateDocumentProjectSubstations namedAs printed
2026-12-01 TEAC
Item 02 - JCPL Supplemental Projects - Presentation p. 3
Red Bank Substation
JCPL-2026-060
Red Bank No figures printed
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 3
Red Arrow Customer
AEP-2026-AP010
None named In service 10/2030
Load 1,000 MW
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 4
Tamarack
AEP-2026-AP009
None named In service 2/2029
Load 1,080 MW
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 5
Project Nutella
AEP-2024-IM015
None named In service 7/31/2029
Load 852 MW
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 7
Flatlick Breaker Replacement
AEP-2026-OH022
Flatlick
Gavin
Status Scoping (Conceptual)
Cost $30.239 M
In service 11/12/2029
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 11
Venator Station
AEP-2026-AP007
Baker
Hanging Rock
Venator Station
Status Scoping (Conceptual)
Cost $324.2 M
In service 10/22/2028
Load 1000 MW
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 15
Razzler Customer Delivery
AEP-2025-OH014, AEP-2026-OH043
Althea Station
Bonzo Switch
Disterdick 69kV Station New
East Haverhill
Franklin Furnace SW
Hanging Rock
Haverhill
Ironton
Jefferson
North Haverhill
Portsmouth
Razzler station New
Status Scoping (Conceptual)
Cost $416.94 M
In service 11/07/2028
Load 1000MW
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 23
Project Avalon
AEP-2026-AP005
Culloden
Gavin
Manilla Ridge New
Status Scoping (Conceptual)
Cost $224.906 M
In service 09/01/2029
Load 1200 MW
2026-12-01 TEAC
Item 03 - AEP Supplemental Projects - Presentation p. 26
Northwest Ohio 345kV Customer Delivery Points & System Reinforcements
AEP-2024-IM014, AEP-2025-OH016, AEP-2025-OH017, AEP-2025-OH018, AEP-2025-OH019
Bosc 1A & 1B (CUSTOMER)
Bosc 2A & 2B (CUSTOMER)
East Lima
Ebersole
Flag City
Fostoria Central
Hillcrest
Lyka New
Maddox Creek
Norse New
North Findlay
Palmer 1 & 2 (CUSTOMER)
Peony 1 & 2 (CUSTOMER)
Pyrite New
Saidin New
Sorenson
Valor 1 & 2 (CUSTOMER)
Wayne Trace
Waynedale
Status Scoping (Conceptual)
Cost $607.548 M
In service 09/26/2031
Load 1,300 MW
2026-12-01 TEAC
Item 04 - EKPC Supplemental Projects - Presentation p. 3
Carroll County
EKPC-2026-007
None named Load 720 MW
2026-12-01 TEAC
Item 05 - PPL Supplemental Projects - Presentation p. 3
Moore's Hill
PPL-2026-0058
None named In service 9/2029
Load 600 MW
2026-12-01 TEAC
Item 05 - PPL Supplemental Projects - Presentation p. 5
Tamarack 500-230kV Substation
PPL-2026-0056
Acahela
Big Bass
Orefield
Sandy Run New
Susquehanna
Tamarack
Wescosville
Status Project Development (Conceptual)
Cost $486 M
In service 05/30/2031
Load 700 MW
2026-12-01 TEAC
Item 05 - PPL Supplemental Projects - Presentation p. 11
Elimsport 230kV Lines
PPL-2026-0031
Elimsport
Sunbury
Status Conceptual
Cost $169.5 M
In service 05/30/2029
Load 300 MW
2026-12-01 TEAC
Item 06 - PECO Supplemental Projects Presentation p. 3
PE-2026-019 Macdade No figures printed
2026-12-01 TEAC
Item 06 - PECO Supplemental Projects Presentation p. 6
220-15 230 kV Line Rebuild
PE-2026-010
Plymouth Meeting
Whitpain
Status Engineering
Cost $13.5M
In service 12/01/2029

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

What a mention is

A mention is a document naming a substation in connection with a project: the need being presented, the proposed solution, or the project's entry in a utility's local plan. The same substation is often named many times as a project moves from need to solution to local plan.

A mention records what the document says. It is not a statement that work will happen, and it says nothing about a substation's capability.

How names and figures are checked

The documents are read by a language model, which is told to copy values exactly as printed and to leave a field empty rather than guess. Every name and figure is then checked against the PDF's own text:

None of this has been reviewed by a person. Every figure links to the page it came from, so it can be checked in seconds.

What this does not say

An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries, and names are not matched to substation location datasets.

Some entries link to the PJM interconnection queue page for a substation of the same name. A link is made only when the presenting utility is the transmission owner recorded on those queue filings, or, for a utility that operates in one state, when every queue filing at that name is in that state. Each link says which of the two it passed. Neither proves the two are the same facility. A name like "Quantum 200" may be a customer's planned station that no public map shows yet.

Statuses are the documents' own words ("Conceptual", "Engineering", "Under Construction"), grouped into a short list so they can be filtered. A printed customer load is the amount a document states for a request, not a measure of a substation's capability.

Source

PJM Interconnection, L.L.C. meeting materials for TEAC, SRRTEP Western, SRRTEP Mid-Atlantic and SRRTEP Southern, plus the utilities' local plan submissions, from October 2024 onward: 670 documents. The materials are public; this site is not affiliated with or reviewed by PJM.