Park Center

Named in 2 PJM planning documents for 2 projects, from November 6, 2024 to October 8, 2025.

Newdescribed as
DOMzone
230kVkV as printed
4mentions

Described as new: “Interconnect the new substation” — source, page 16

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Park Center 230kV Delivery - DEV
DOM-2020-0043- UPDATE · s2622.1
Engineering $27.0 M 11/21/2025 41.0 MW 2025-10-08
TEAC
Dominion Transmission Zone: Supplemental Towerview 230kV Delivery - DEV
DOM-2023-0004 · s3670
Engineering $13.0 M 11/30/2027 300.0 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 70
Dominion Transmission Zone: Supplemental Park Center 230kV Delivery - DEV “new substation (Park Center)”
230kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 75
Dominion Transmission Zone: Supplemental Towerview 230kV Delivery - DEV No role wording
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 16
Dominion Transmission Zone: Supplemental Park Center 230kV Delivery - DEV “Interconnect the new substation”
230kV
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 18
Dominion Transmission Zone: Supplemental Towerview 230kV Delivery - DEV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.