Substation Scout

Greenfield

Named in 13 PJM planning documents for 11 projects, from November 6, 2024 to October 6, 2026.

Existingdescribed as
ATSIzone
138 kV, 69 kVkV as printed
14mentions

Also printed as: Greenfield Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Cluster 2 (ATSI)
b3925.1
Not printed $217.32M 6/1/2029 Not printed 2025-01-07
TEAC
Greenfield 69 kV B-24, B-272, B-274 CB Replacement
b3984.1
Not printed $1.53M 6/1/2030 Not printed 2025-11-14
SRRTEP Western
Cluster 2 (ATSI) Not printed $217.32M 6/1/2029 Not printed 2024-12-03
TEAC
Cluster 2 (ATSI) Not printed Not printed Not printed Not printed 2024-11-06
TEAC
Rebuild/Reconductor existing 138 kV lines/Terminal upgrades at 345 kV substations Not printed 265.1 Not printed Not printed 2024-11-19
TEAC
Greenfield 69 kV B-24, B-272, B-274 CB Replacement Not printed $1.53M 6/1/2030 Not printed 2025-10-17
SRRTEP Western
New Departure 345 kV Customer Connection
ATSI-2024-056 · s3660.1
Not printed $99.1 M November 28, 2029 Not printed 2025-10-08
TEAC
Black River-Shinrock 69 kV Rebuild
ATSI-2024-072
Conceptual $67.65M 12/31/2029 Not printed 2026-07-17
SRRTEP Western
Huron Area
ATSI-2025-001
Not printed Not printed Not printed approximately 40 MVA 2025-01-17
SRRTEP Western
Lemoyne Substation Upgrades for MISO Tranche 2.1
ATSI-2025-004 · s3844.1
Not printed $100.86M 6/1/2032 Not printed 2026-10-06
TEAC
Greenfield Substation
ATSI-2026-047
Not printed Not printed Not printed Not printed 2026-07-17
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named AXTEL; BAUMHART; BLACK RIVER; SHINROCK; WASHINGTON → AXTEL; BAUMHART; BLACK RIVER; GREENFIELD; SHINROCK; WASHINGTON 2024-10-18 2026-07-17
Substations named AXTEL; BAUMHART; BLACK RIVER; GREENFIELD; SHINROCK; WASHINGTON → SHINROCK 2026-07-17 2026-10-06
Cost estimate $15.6 M → $100.86 M 2025-03-04 2025-12-08
Substations named LAPLAISANCE CREEK; LEMOYNE; MAJESTIC; MAPLE → LEMOYNE 2025-02-04 2025-03-04
Substations named LEMOYNE → GREENFIELD; LAKEVIEW; LEMOYNE; OTTAWA 2025-03-04 2025-12-08
Substations named GREENFIELD; LAKEVIEW; LEMOYNE; OTTAWA → GREENFIELD; LEMOYNE; OTTAWA 2025-12-08 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2026 p. 19
Lemoyne Substation Upgrades for MISO Tranche 2.1 “At Greenfield Substation: Install one circuit breaker and associated disconnects.”
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 19
Lemoyne Substation Upgrades for MISO Tranche 2.1 “At Greenfield Substation: Install one circuit breaker and associated disconnects.”
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2025 RTEP p. 30
New Departure 345 kV Customer Connection “Re-terminate the lines from Ford Substation and Greenfield Substation into the New Departure Substation.”
138 kV
2026-07-17 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 26
Black River-Shinrock 69 kV Rebuild No role wording
69 kV
2026-07-17 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 5
Greenfield Substation “The Greenfield Substation control house is congested.”
2025-12-08 TEAC
Item 04 - ATSI Supplemental Projects p. 4
Lemoyne Substation Upgrades for MISO Tranche 2.1 “At Greenfield Substation: Install one circuit breaker”
138 kV
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 99
Greenfield 69 kV B-24, B-272, B-274 CB Replacement “Replace overdutied Greenfield 69 kV circuit breakers B-24, B-272, B-274”
69 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 94
Greenfield 69 kV B-24, B-272, B-274 CB Replacement “Greenfield 69 kV B-24, B-272, B-274 CB Replacement”
69 kV
2025-10-08 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 30
New Departure 345 kV Customer Connection “Upgrade relaying/adjust relay settings at Greenfield, Nasa and Ford substations”
138 kV
2025-01-17 SRRTEP Western
Item 05 - ATSI Supplemental Projects p. 4
Huron Area “opening breaker at Greenfield Substation”
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 51
Cluster 2 (ATSI) No role wording
138 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 72
Cluster 2 (ATSI) No role wording
138 kV
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
Rebuild/Reconductor existing 138 kV lines/Terminal upgrades at 345 kV substations No role wording
138 kV
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 58
Cluster 2 (ATSI) No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this