Keelette

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to November 15, 2024.

Existingdescribed as
AEPzone
34.5kV, 69kVkV as printed
4mentions

Also printed as: Keelette Switch

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline Hartford Transformer Tap Change Replacement
b3872.1
Not printed $0.1M 6/1/2026 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline Hartford Transformer Tap Change Replacement Not printed $0.1M 6/1/2026 Not printed 2024-10-18
SRRTEP Western
Rothadew Area Improvements
AEP-2022-IM013 · s3136.1-.7
Conceptual $7.89M 7/27/2027 28MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 49
Rothadew Area Improvements “Keelette, Sister Lakes, Gearcon Sw., Rothadew,: Energize to 69kV”
69kV
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 16
AEP Transmission Zone: Baseline Hartford Transformer Tap Change Replacement No role wording
34.5kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 15
AEP Transmission Zone: Baseline Hartford Transformer Tap Change Replacement No role wording
34.5kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 49
Rothadew Area Improvements “Energize to 69kV”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this