Substation Scout

Firebrick

Named in 2 PJM planning documents for 2 projects, from October 18, 2024 to November 15, 2024.

Existingdescribed as
AEPzone
69 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline Firebrick – Jefferson 69kV Reconductor
b3875.1
Not printed $8.5M 4/1/2029 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline Firebrick – Jefferson 69kV Reconductor Not printed $8.5M 4/1/2029 Not printed 2024-10-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 29
AEP Transmission Zone: Baseline Firebrick – Jefferson 69kV Reconductor “Remote End (Line protection settings) would need to be updated at Firebrick and Lick.”
69 kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 27
AEP Transmission Zone: Baseline Firebrick – Jefferson 69kV Reconductor “updated at Firebrick and Lick. Replace 600A Switches at Jefferson and replace 477 AA 19 sub conductor at Firebrick.”
69 kV