East Leipsic

Named in 6 PJM planning documents for 3 projects, from October 18, 2024 to October 6, 2026.

Existingdescribed as
AEPzone
138 kV, 138/69/34.5kV, 138kVkV as printed
6mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline East Leipsic – AE2-072 (Lammer) Sag Study and Mitigation
b3888.1
Not printed $2.5M 4/1/2029 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline East Leipsic – AE2-072 (Lammer) Sag Study and Mitigation Not printed $2.5M 4/1/2029 Not printed 2024-10-18
SRRTEP Western
East Leipsic, OH
AEP-2025-OH011 · s3837.1
Engineering $10.624 M 11/01/2027 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 31
East Leipsic, OH “Replace transformer #3 with 138/69/34.5kV three winding 90MVA unit”
138/69/34.5kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 31
East Leipsic, OH “Replace transformer #3 with 138/69/34.5kV three winding 90MVA unit”
138/69/34.5kV
2025-10-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 8
East Leipsic, OH “Replace transformer #3 with 138/69/34.5kV three winding 90MVA unit and install associated low side 69kV circuit breaker”
138/69/34.5kV
2025-07-18 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 10
East Leipsic, OH “Station: East Leipsic 138kV”
138kV
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 39
AEP Transmission Zone: Baseline East Leipsic – AE2-072 (Lammer) Sag Study and Mitigation No role wording
138 kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 37
AEP Transmission Zone: Baseline East Leipsic – AE2-072 (Lammer) Sag Study and Mitigation No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.