Allen

Named in 4 PJM planning documents for 3 projects, from November 6, 2024 to October 6, 2026.

Existingdescribed as
AEPzone
138 kV, 345/138kV, 345kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
West Cluster Recommended Selection (2nd Read)
b4068.1
Not printed $2,768.0M 10/1/2032 Not printed 2026-01-06
TEAC
New Haven, Indiana
AEP-2023-IM026 · s3750.1-4
Conceptual $169.1 M 07/01/2029 1200MW 2026-10-06
TEAC
Fort Wayne, IN
AEP-2024-IM014
Not printed Not printed Not printed Not printed 2024-11-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ALLEN; ROBISON PARK; ZODIAC → ALLEN; ZODIAC 2024-11-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 3
New Haven, Indiana “Expand Allen station”
345/138kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 3
New Haven, Indiana “Expand Allen station with 2x additional 345/138kV transformers”
345/138kV
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 53
West Cluster Recommended Selection (2nd Read) “Replace bus conductor at Allen station.”
138 kV
2024-11-06 TEAC
Item 07 - AEP Supplemental Projects p. 3
Fort Wayne, IN No role wording
345kV
2024-11-06 TEAC
Item 07 - AEP Supplemental Projects p. 8
New Haven, Indiana “Expand Allen station”
345/138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.