Substation Scout

Bexley

Named in 4 PJM planning documents for 2 projects, from October 18, 2024 to October 8, 2025.

Existingdescribed as
AEPzone
138 kV, 138kVkV as printed
6mentions

Also printed as: Bexley Station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone M-3 Process Columbus, OH
AEP-2023-OH004 · s3577.1-.3
Conceptual $7.233 M 09/30/2026 Not printed 2025-10-08
TEAC
AEP Transmission Zone M-3 Process Franklin, OH
AEP-2024-OH033 · s3593.1-.3
Conceptual $10.793 M 11/30/2026 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BEXLEY; DREW; ST CLAIR AVE → BEXLEY; DREW; ST CLAIR AVE STATIONS 2025-10-08 Not reported
Substations named BEXLEY; DREW; ST CLAIR; ST CLAIR AVE → BEXLEY; DREW; ST CLAIR AVE 2024-11-15 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 14
AEP Transmission Zone M-3 Process Franklin, OH “Remote end work will be performed at Bexley”
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 4
AEP Transmission Zone M-3 Process Columbus, OH “Bexley Station 138kV: • AEP Ohio has indicated they have equipment rehabilitation needs at the station.”
138kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 14
AEP Transmission Zone M-3 Process Franklin, OH “Remote end work will be performed at Bexley”
138 kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 6
AEP Transmission Zone M-3 Process Columbus, OH “work will be performed to address asset renewal concerns associated with the site and transmission equipment including work to allow for the retirement of the existing 40 kV yard at the station”
138kV
2024-11-15 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 8
AEP Transmission Zone M-3 Process Franklin, OH “Remote end work will be performed at Bexley and St. Clair Ave stations”
138 kV
2024-10-18 SRRTEP Western
Item 06 - AEP Supplemental Projects p. 9
AEP Transmission Zone M-3 Process Columbus, OH “At Bexley, work will be performed to address asset renewal concerns”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.