Lackawanna

Named in 12 PJM planning documents for 8 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
PPLzone
230-69kV, 230/69kV, 230kV, 500 kV, 500kV, 69kVkV as printed
18mentions

Also printed as: Lackawanna substation

PJM interconnection queue

A PJM queue substation page has the same name: Lackawanna (PA) — 7 queue requests filed, 4 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Pocono area Evaluation Progress Not printed $4.93 10/30/2027 Not printed 2024-11-06
TEAC
Lackawanna, PA
PPL-2024-0015 · s3552
Conceptual $6.3 M 12/31/2026 Not printed 2025-10-08
TEAC
Callender Gap, PA
PPL-2025-0005
Conceptual $73.5 M 05/30/2028 500 MW 2026-10-06
TEAC
Big Bass, PA
PPL-2025-0012
Conceptual $186.875 M 05/30/2028 1,500 MW 2026-10-06
TEAC
Lackawana, PA
PPL-2025-0013
Conceptual $74.9 M 07/30/2028 1,400 MW 2026-10-06
TEAC
Archbald Mountain, PA
PPL-2025-0014
Conceptual $220 M 05/30/2028 1,000 MW 2026-02-03
TEAC
Callender Gap, PA
PPL-2026-0002
Conceptual $76.5 M 05/30/2029 1,200 MW 2026-05-08
TEAC
Tinker Tap Strengthening
PPL-2026-0017
Conceptual $34.6 M 11/30/2029 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 05/2027 → 05/30/2028 2025-05-06 2025-06-05
Substations named CALLENDER GAP; HOPATCONG; LACKAWANNA; PAUPACK → CALLENDER GAP; LACKAWANNA; PAUPACK 2025-06-05 2026-10-06
In-service date 05/2027 → 05/30/2028 2025-07-08 2025-09-09
In-service date 07/2028 → 07/30/2028 2025-09-09 2025-10-08
In-service date 05/2027 → 05/30/2028 2025-09-09 2026-02-03
In-service date 5/2028 → 05/30/2029 2026-03-10 2026-05-08
Substations named ELK MOUNTAIN; TINKER → ELK MOUNTAIN; GREENFIELD; TINKER 2026-03-18 2026-04-14
Substations named ELK MOUNTAIN; GREENFIELD; TINKER → BROOKSIDE; ELK MOUNTAIN; GREENFIELD; LACKAWANNA; TINKER 2026-04-14 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 15
Callender Gap, PA “Install one new 230kV breaker, 230kV dead-end, and ancillary equipment in Bay #1 at Lackawanna 230kV Yard”
230kV
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 23
Lackawana, PA “Replace one 230kV breaker and two MODs in Bay #3 at Lackawanna 230kV”
230kV
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 27
Big Bass, PA “Replace two 230kV breakers and four MODs in Bay #3 at Lackawanna 230kV”
230kV
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 93
Tinker Tap Strengthening No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 15
Callender Gap, PA “Install one new 230kV breaker, 230kV dead-end, and ancillary equipment in Bay #1 at Lackawanna 230kV Yard”
230kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 23
Lackawana, PA “Replace one 230kV breaker and two MODs in Bay #3 at Lackawanna 230kV”
230kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 27
Big Bass, PA “Replace two 230kV breakers and four MODs in Bay #3 at Lackawanna 230kV”
230kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 93
Tinker Tap Strengthening No role wording
69kV
2026-09-08* SRRTEP Mid-Atlantic
PPL local plan submission for 2025 RTEP p. 13
Lackawanna, PA “replacement of the existing 230-69kV Lackawanna Transformer 2”
230-69kV
2026-05-08 TEAC
Item 06 - PPL Supplemental Projects p. 10
Callender Gap, PA “Install a +/-200MVAR STATCOM at Lackawanna 230kV yard”
230kV
2026-02-03 TEAC
Item 07 - PPL Supplemental Projects p. 7
Archbald Mountain, PA No role wording
500kV
2025-10-08 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2025 p. 12
Lackawanna, PA “The Lackawanna substation 230/69kV Transformer 2 is about 32 years old and is considered high risk due to its material condition and maintenance history.”
230/69kV
2025-10-08 TEAC
Item 09 - PPL Supplemental Projects p. 4
Lackawana, PA “Replace one 230kV breaker and two MODs in Bay #3 at Lackawanna 230kV”
230kV
2025-09-09 TEAC
Item 09 - PPL Supplemental Projects p. 10
Big Bass, PA “Replace two 230kV breakers and four MODs in Bay #3 at Lackawanna 230kV”
230kV
2025-06-05 TEAC
Item 05 - PPL Supplemental Projects p. 4
Callender Gap, PA “Install one new 230kV breaker, 230kV dead end, and ancillary equipment in Bay #1 at Lackawanna 230kV Yard”
230kV
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 49
Pocono area Evaluation Progress No role wording
500 kV
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 16
Lackawanna, PA “in-kind replacement of the existing 230-69kV Lackawanna Transformer 2”
230-69kV
2024-10-08 TEAC
Item 07 - PPL Supplemental Projects p. 7
Lackawanna, PA No role wording
230/69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.