Substation Scout

Pequest River

Named in 7 PJM planning documents for 4 projects, from October 8, 2024 to September 17, 2026.

Existingdescribed as
JCPLzone
115 kV, 115-34.5 kVkV as printed
9mentions

Also printed as: Pequest River Substation

PJM interconnection queue

A PJM queue substation page has the same name: Pequest River (NJ) — 5 queue requests filed, 3 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
JCPL Transmission Zone M-3 Process Morris Park Substation
JCPL-2023-011 · s3611.1
Not printed $15.4M 1/29/2027 13 MW 2025-10-08
TEAC
Pequest River Substation
JCPL-2023-055 · s3283.1
Not printed $4.23M 5/1/2025 Not printed 2024-10-08
TEAC
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer
JCPL-2024-037 · s3638.1
Not printed $6.9 M 01/30/2030 Not printed 2025-10-08
TEAC
Gilbert - Pequest River 115 kV Line Rebuild
JCPL-2024-039
Conceptual $81.55 M 06/29/2029 Not printed 2026-09-17
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-09-17 SRRTEP Mid-Atlantic
Item 01 - JCPL Supplemental Projects p. 18
Gilbert - Pequest River 115 kV Line Rebuild No role wording
115 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 31
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer “Replace No. 1 115-34.5 kV Transformer at Pequest River Substation”
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 4
JCPL Transmission Zone M-3 Process Morris Park Substation No role wording
115 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 55
Pequest River Substation “Replace the 115-34.5 kV No. 2 Transformer at Pequest River”
115-34.5 kV
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 31
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer “Replace No. 1 115-34.5 kV Transformer at Pequest River Substation”
115-34.5 kV
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 4
JCPL Transmission Zone M-3 Process Morris Park Substation No role wording
115 kV
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 10
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer “Replace No. 1 115-34.5 kV Transformer at Pequest River Substation”
2024-11-06 TEAC
Item 05 - JCPL Supplemental Projects p. 3
JCPL Transmission Zone M-3 Process Morris Park Substation No role wording
115 kV
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 54
Pequest River Substation “The 115-34.5 kV No. 2 Transformer at Pequest River Substation was manufactured approximately 50 years ago”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this