Pequest River
Named in 7 PJM planning documents for 4 projects, from October 8, 2024 to September 17, 2026.
Existingdescribed as
JCPLzone
115 kV, 115-34.5 kVkV as printed
9mentions
Also printed as: Pequest River Substation
PJM interconnection queue
A PJM queue substation page has the same name: Pequest River (NJ) — 5 queue requests filed, 3 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| JCPL Transmission Zone M-3 Process Morris Park Substation JCPL-2023-011 · s3611.1 |
Not printed | $15.4M | 1/29/2027 | 13 MW | 2025-10-08 TEAC |
| Pequest River Substation JCPL-2023-055 · s3283.1 |
Not printed | $4.23M | 5/1/2025 | Not printed | 2024-10-08 TEAC |
| JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer JCPL-2024-037 · s3638.1 |
Not printed | $6.9 M | 01/30/2030 | Not printed | 2025-10-08 TEAC |
| Gilbert - Pequest River 115 kV Line Rebuild JCPL-2024-039 |
Conceptual | $81.55 M | 06/29/2029 | Not printed | 2026-09-17 SRRTEP Mid-Atlantic |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-17 | SRRTEP Mid-Atlantic Item 01 - JCPL Supplemental Projects p. 18 |
Gilbert - Pequest River 115 kV Line Rebuild | No role wording 115 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2025 RTEP p. 31 |
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer | “Replace No. 1 115-34.5 kV Transformer at Pequest River Substation” |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2025 RTEP p. 4 |
JCPL Transmission Zone M-3 Process Morris Park Substation | No role wording 115 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2024 RTEP p. 55 |
Pequest River Substation | “Replace the 115-34.5 kV No. 2 Transformer at Pequest River” 115-34.5 kV |
| 2025-10-08 | TEAC Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 31 |
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer | “Replace No. 1 115-34.5 kV Transformer at Pequest River Substation” 115-34.5 kV |
| 2025-10-08 | TEAC Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 4 |
JCPL Transmission Zone M-3 Process Morris Park Substation | No role wording 115 kV |
| 2025-04-10 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 10 |
JCPL Transmission Zone M-3 Process Pequest River No. 1 115-34.5 kV Transformer | “Replace No. 1 115-34.5 kV Transformer at Pequest River Substation” |
| 2024-11-06 | TEAC Item 05 - JCPL Supplemental Projects p. 3 |
JCPL Transmission Zone M-3 Process Morris Park Substation | No role wording 115 kV |
| 2024-10-08 | TEAC Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 54 |
Pequest River Substation | “The 115-34.5 kV No. 2 Transformer at Pequest River Substation was manufactured approximately 50 years ago” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.