Englishtown
Named in 14 PJM planning documents for 10 projects, from October 8, 2024 to October 16, 2026.
Also printed as: Englishtown Substation
PJM interconnection queue
A PJM queue substation page has the same name: Englishtown (NJ) — 2 queue requests filed, 0 active.
Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Jamesburg – Monroe 34.5 kV Line b4016.1 |
Not printed | $6.35 M | 6/1/2030 | Not printed | 2025-11-13 SRRTEP Mid-Atlantic |
| Jamesburg – Monroe 34.5 kV Line | Not printed | $6.35 M | 6/1/2030 | Not printed | 2025-10-16 SRRTEP Mid-Atlantic |
| Automatic Restoration Projects JCPL-2023-024 · s3244.1 |
Not printed | $2.56 | 10/15/2025 | Not printed | 2024-10-08 TEAC |
| Deep Run – Englishtown 115 kV DRE2 Line JCPL-2023-056 · s3966.1 |
Not printed | $36.34M | 05/18/2029 | Not printed | 2026-10-06 TEAC |
| Deep Run – Englishtown 115 kV DRE1 Line JCPL-2023-066 · s3967.1 |
Not printed | $38.88M | 05/19/2028 | Not printed | 2026-10-06 TEAC |
| JCPL Transmission Zone M-3 Process Deep Run No. 2 115-34.5 kV Transformer JCPL-2024-026 · s3614.1 |
Not printed | $8M | 12/31/2027 | Not printed | 2026-09-08* SRRTEP Mid-Atlantic |
| Englishtown No. 1 115-34.5 kV Transformer JCPL-2024-028 · s3618.1 |
Not printed | $7M | 12/31/2027 | Not printed | 2025-10-08 TEAC |
| Englishtown No. 6 230-34.5 kV Transformer JCPL-2025-005 · s3962.1 |
Not printed | $2.06 M | 12/17/2026 | Not printed | 2026-10-06 TEAC |
| Jerseyville - Smithburg 34.5 kV X752 Line JCPL-2026-024 |
Not printed | Not printed | Not printed | Not printed | 2026-09-17 SRRTEP Mid-Atlantic |
| Wyckoff Street Substation JCPL-2026-050 |
Not printed | Not printed | Not printed | Not printed | 2026-10-16 SRRTEP Mid-Atlantic |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Substations named | DEEP RUN → DEEP RUN; ENGLISHTOWN; RARITAN RIVER | 2025-10-08 | Not reported |
| Substations named | ENGLISHTOWN → DEEP RUN; ENGLISHTOWN; WYCKOFF ST | 2025-10-08 | Not reported |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-16 | SRRTEP Mid-Atlantic Item 06 - JCPL Supplemental Projects Presentation p. 6 |
Wyckoff Street Substation | No role wording 34.5 kV |
| 2026-10-06 | TEAC Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 22 |
Englishtown No. 6 230-34.5 kV Transformer | “Replace limiting substation equipment of transformer leads to exceed the Englishtown No. 6 Transformer ratings” 230-34.5 kV |
| 2026-10-06 | TEAC Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 32 |
Deep Run – Englishtown 115 kV DRE2 Line | “At Englishtown Substation, replace relays and substation conductor” 115 kV |
| 2026-10-06 | TEAC Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 34 |
Deep Run – Englishtown 115 kV DRE1 Line | “At Englishtown Substation, replace relays and substation conductor” 115 kV |
| 2026-10-01* | SRRTEP Mid-Atlantic JCPL local plan submission for 2026 RTEP p. 22 |
Englishtown No. 6 230-34.5 kV Transformer | “Replace limiting substation equipment of transformer leads” 230-34.5 kV |
| 2026-10-01* | SRRTEP Mid-Atlantic JCPL local plan submission for 2026 RTEP p. 32 |
Deep Run – Englishtown 115 kV DRE2 Line | “At Englishtown Substation, replace relays and substation conductor.” |
| 2026-10-01* | SRRTEP Mid-Atlantic JCPL local plan submission for 2026 RTEP p. 34 |
Deep Run – Englishtown 115 kV DRE1 Line | “At Englishtown Substation, replace relays and substation conductor.” |
| 2026-09-17 | SRRTEP Mid-Atlantic Item 01 - JCPL Supplemental Projects p. 7 |
Jerseyville - Smithburg 34.5 kV X752 Line | No role wording 34.5 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2025 RTEP p. 19 |
JCPL Transmission Zone M-3 Process Deep Run No. 2 115-34.5 kV Transformer | No role wording |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2025 RTEP p. 23 |
Englishtown No. 1 115-34.5 kV Transformer | “Replace the No. 1 115-34.5 kV Transformer at Englishtown Substation” |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2024 RTEP p. 14 |
Automatic Restoration Projects | “At Englishtown, replace relaying” 34.5 kV |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 14 |
Deep Run – Englishtown 115 kV DRE2 Line | “At Englishtown Substation, replace relays and substation conductor” 115 kV |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 16 |
Deep Run – Englishtown 115 kV DRE1 Line | “At Englishtown Substation, replace relays and substation conductor” 115 kV |
| 2025-12-08 | TEAC Item 06 - JCPL Supplemental Projects p. 8 |
Englishtown No. 6 230-34.5 kV Transformer | “Replace limiting substation equipment of transformer leads to exceed the Englishtown No. 6 Transformer ratings.” 230-34.5 kV |
| 2025-11-13 | SRRTEP Mid-Atlantic Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 28 |
Jamesburg – Monroe 34.5 kV Line | No role wording |
| 2025-11-04 | TEAC Item 05 - JCPL Supplemental Projects p. 3 |
Englishtown No. 6 230-34.5 kV Transformer | No role wording 230-34.5 kV |
| 2025-10-16 | SRRTEP Mid-Atlantic Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 28 |
Jamesburg – Monroe 34.5 kV Line | No role wording 34.5 kV |
| 2025-10-08 | TEAC Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 23 |
Englishtown No. 1 115-34.5 kV Transformer | “Replace the No. 1 115-34.5 kV Transformer at Englishtown Substation” 115-34.5 kV |
| 2024-11-14 | SRRTEP Mid-Atlantic Item 06 - JCPL Supplemental Projects p. 11 |
Englishtown No. 1 115-34.5 kV Transformer | “Replace the No. 1 115-34.5 kV Transformer at Englishtown Substation” 115-34.5 kV |
| 2024-10-08 | TEAC Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 14 |
Automatic Restoration Projects | “At Englishtown, replace relaying” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.