North Oakford
Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 8, 2025.
Existingdescribed as
APSzone
138 kVkV as printed
5mentions
Also printed as: North Oakford Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Penn-North Oakford 138 kV New Customer APS-2023-008 · s3125.1 |
Not printed | $5.4M | 12/31/2024 | Not printed | 2024-10-08 TEAC |
| Stony Springs Junction Area APS-2023-022 · s3575.1 |
Not printed | $13.6M | 6/22/2027 | ~25 MW | 2025-10-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Substations named | DELMONT; HARRISON CITY; HEMPFIELD; LUXOR; NORTH GREENSBURG; NORTH OAKFORD; PENN; STONY SPRINGS JUNCTION → DELMONT; HARRISON CITY; HEMPFIELD; LUXOR; NORTH GREENSBURG; NORTH OAKFORD; NORTH OAKFORD TAP; PENN; SOUTH OAKFORD TAP; STONY SPRINGS JUNCTION | 2024-11-15 | 2025-10-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 13 |
Penn-North Oakford 138 kV New Customer | No role wording 138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2025 RTEP p. 14 |
Stony Springs Junction Area | “At North Oakford Substation: Install full SCADA control” 138 kV |
| 2025-10-08 | TEAC Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 14 |
Stony Springs Junction Area | “At North Oakford Substation: Install full SCADA control on the existing switch.” 138 kV |
| 2024-11-15 | SRRTEP Western Item 05 - APS Supplemental projects p. 16 |
Stony Springs Junction Area | “At North Oakford Substation: Install full SCADA control on the existing switch.” 138 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 13 |
Penn-North Oakford 138 kV New Customer | No role wording 138 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.