Named in 7 PJM planning documents for 5 projects, from November 6, 2024 to July 7, 2026.

Existingdescribed as
COMEDzone
138 kV, 138kV, 345/138 kV, 345KVkV as printed
10mentions

Also printed as: Itasca Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Itasca
ComEd-2023-009 · s3581.1
Engineering $9.9M 12/1/26 272.7 MW 2025-10-08
TEAC
Customer in Elk Grove
ComEd-2024-003 · s3584.1; s3584.2
Engineering $319.4M 12/31/2027 (s3584.1), 12/31/2028 (s3584.2) 250 MW 2025-09-19
SRRTEP Western
Cluster 2
ComEd-2024-004 · s3583.1, s3583.2
Engineering $40.6M 12/31/2026 (s3583.1), 12/31/2027 (s3583.2) 260 MW 2025-10-08
TEAC
345KV STATCOMS
ComEd-2024-014, ComEd-2024-022, ComEd-2025-005, ComEd-2025-011, ComEd-2025-013, ComEd-2025-015, ComEd-2025-016, ComEd-2025-020
Conceptual $472.0M 06/01/2031 Not printed 2026-07-07
TEAC
Des Plaines 345 kV CBs
ComEd-2025-026
Conceptual $3.9M 12/31/2027 Not printed 2025-12-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $319.4M → $289.4M 2025-09-19 2025-10-08
Status engineering (Engineering) → conceptual (Conceptual) 2025-09-19 2025-10-08
Substations named COMED DIERKING; COMED ELK GROVE EAST; COMED ITASCA; COMED PINE → DIERKING; ELK GROVE EAST; ITASCA; PINE 2025-10-08 Not reported
Cost estimate $14.31 M → $40.6M 2024-12-03 2025-10-08
In-service date 6/1/2029 → 12/31/2026 (s3583.1), 12/31/2027 (s3583.2) 2024-12-03 2025-10-08
Substations named BUSSE; DES PLAINES; ITASCA → ELK GROVE EAST; ITASCA 2024-12-03 2025-10-08
Cost estimate $35.3 M → $472.0M 2025-09-09 2026-07-07
In-service date 5/1/2028 → 06/01/2031 2025-09-09 2026-07-07
Substations named LASALLE; PLANO → BRYON; CHARTER GROVE; HIAWATHA; ITASCA; SILVER LAKE; WAYNE 2025-09-09 2026-07-07
Substations named DES PLAINES → DES PLAINES; ITASCA 2025-11-04 2025-12-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 14
Cluster 2 “install 2 new 345/138 kV, 420 MVA autotransformers at Itasca substation”
345/138 kV
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 17
Customer in Elk Grove “underground lines from ComEd Itasca substation”
138kV
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 9
Customer in Itasca “expanding the bus at Itasca with 2 new bays”
138 kV
2026-07-07 TEAC
Item 12 - ComEd Supplemental Projects p. 13
345KV STATCOMS “Install +/-350 MVAR 345KV STATCOM, 1-150 MVAR 345KV Capacitor Banks and three associated 345KV Circuit Breakers at Itasca Substation”
345KV
2025-12-08 TEAC
Item 09 - ComEd Supplemental Projects p. 8
Des Plaines 345 kV CBs No role wording
2025-10-08 TEAC
Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 14
Cluster 2 “Install 2 new 345 kV CBs, 2 new 138 kV CBs and install 2 new 345/138 kV, 420 MVA autotransformers at Itasca substation”
345/138 kV
2025-10-08 TEAC
Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 9
Customer in Itasca “expanding the bus at Itasca with 2 new bays”
138 kV
2025-09-19 SRRTEP Western
Item 04 - ComEd Supplemental Projects p. 8
Customer in Elk Grove “lines from ComEd Itasca substation”
138kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 57
Cluster 2 “circuit breakers at Itasca substation”
345/138 kV
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 38
Cluster 2 “circuit breakers at Itasca substation”
345/138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.