Substation Scout

Churchland

Named in 2 PJM planning documents for 2 projects, from November 6, 2024 to October 8, 2025.

Not stateddescribed as
DOMzone
—kV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency
DOM-2022-0058
Cancelled Not printed Not printed Not printed 2024-11-06
TEAC
Dominion Transmission Zone: Supplemental NIT Substation 230kV Delivery - DEV
DOM-2023-0006 · s3697.1
Under construction $5.7 M 12/31/2024 49.3 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 77
Dominion Transmission Zone: Supplemental NIT Substation 230kV Delivery - DEV No role wording
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 19
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency No role wording
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 21
Dominion Transmission Zone: Supplemental NIT Substation 230kV Delivery - DEV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.