Mentions: February 2025
Each row is one PJM document naming substations for one project, newest first. Atom feed
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
| Date | Document | Project | Substations named | As printed |
|---|---|---|---|---|
| 2025-02-14 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 3 |
Versailles, OH AMPT-2024-001 |
Baker Rd New Baker Road New Greenlawn Russia Subler Drive New Water Street |
Status pre-engineering (Engineering) Cost $66.6 M In service 06/30/2028 Load 16 MW |
| 2025-02-14 | SRRTEP Western Item 02 - DLCO Supplemental Projects p. 3 |
Dravosburg, PA DLC-2025-002 |
Dravosburg Substation | No figures printed |
| 2025-02-14 | SRRTEP Western Item 02 - DLCO Supplemental Projects p. 4 |
Carson, PA DLC-2025-001 |
Carson Substation | No figures printed |
| 2025-02-14 | SRRTEP Western Item 02 - DLCO Supplemental Projects p. 5 |
Findlay, PA DLC-2025-003 |
Findlay Substation | No figures printed |
| 2025-02-14 | SRRTEP Western Item 02 - DLCO Supplemental Projects p. 6 |
Neville, PA DLC-2024-004 |
Neville Substation | No figures printed |
| 2025-02-14 | SRRTEP Western Item 03 - ComEd Supplemental Projects p. 3 |
ComEd-2025-003 | Devon Northwest Rosehill Skokie |
No figures printed |
| 2025-02-14 | SRRTEP Western Item 03 - ComEd Supplemental Projects p. 5 |
138 kV L10301 Wave Trap at Lombard ComEd-2025-001 |
Lisle Lombard |
Status Engineering Cost $ 0.15 M In service 12/31/2025 |
| 2025-02-14 | SRRTEP Western Item 03 - ComEd Supplemental Projects p. 7 |
138 kV L10302 Wave Trap at Lombard ComEd-2025-002 |
Lisle Lombard |
Status Conceptual Cost $ 0.15 M In service 12/31/2027 |
| 2025-02-14 | SRRTEP Western Item 03 - ComEd Supplemental Projects p. 9 |
Customer in Aurora ComEd-2024-022 |
Aurora Bilter Road Electric Junction |
Status Engineering Cost $0M In service 12/31/27 Load 91 MW |
| 2025-02-14 | SRRTEP Western Item 04 - APS Supplemental Projects p. 3 |
Shepherdstown, WV/Sleepy Hollow, WV APS-2025-005 |
Shepherdstown Substation Sleepy Hollow |
No figures printed |
| 2025-02-14 | SRRTEP Western Item 04 - APS Supplemental Projects p. 7 |
Misoperation Relay Projects APS-2024-114 |
Buckhannon Substation French Creek |
Status Conceptual Cost $7.1 M In service 03/30/2029 |
| 2025-02-14 | SRRTEP Western Item 04 - APS Supplemental Projects p. 8 |
Misoperation Relay Projects APS-2024-116 |
Weirton Substation Wylie Ridge Substation |
Status Conceptual Cost $7.04 M In service 04/27/2029 |
| 2025-02-14 | SRRTEP Western Item 04 - APS Supplemental Projects p. 9 |
Misoperation Relay Projects APS-2024-090 |
Tiltonsville Windsor |
Status Conceptual Cost $1.05 M In service 11/20/2026 |
| 2025-02-14 | SRRTEP Western Item 04 - APS Supplemental Projects p. 12 |
Albright Substation APS-2024-072 |
Albright Substation Snowy Creek Tap |
Status Conceptual Cost $1.69 M In service 08/20/2029 |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 3 |
Fort Wayne, IN AEP-2025-IM001 |
None named | In service 12/2027 Load 17MW |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 4 |
Green, IN AEP-2025-IM002 |
German | No figures printed |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 5 |
Elcona Tap, IN AEP-2025-IM003 |
Elcona | No figures printed |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 6 |
Fayette County, WV AEP-2025-AP004 |
None named | In service 2025 Load 7.5 MW |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 7 |
Harrison, OH/Madison, OH AEP-2025-OH001 |
None named | In service 12/2026 Load 17.5 MW |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 8 |
Lazelle, OH/Bush, OH AEP-2025-OH002 |
Busch Lazelle |
No figures printed |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 9 |
Greif, OH/Huntley, OH/Busch, OH/Lazelle, OH AEP-2025-OH003 |
Busch Greif Huntley Lazelle |
No figures printed |
| 2025-02-14 | SRRTEP Western Item 05 - AEP Supplemental Projects p. 11 |
Hannibal, OH AEP-2024-OH039 |
Hannibal Kammer North Sub Station |
Status Scoping (Conceptual) Cost $0.392 M In service 07/17/2025 Load 200 MW |
| 2025-02-14 | SRRTEP Western Item 06 - DEOK Supplemental Projects p. 3 |
Markley DEOK-2024-003 |
Markley | Status Engineering Cost $1,080,019 In service 12/11/2026 |
| 2025-02-14 | SRRTEP Western Item 06 - DEOK Supplemental Projects p. 5 |
Turfway DEOK-2024-004 |
Aero Constance Limaburg Oakbrook Turfway New |
Status Scoping (Conceptual) Cost $13M In service 07-25-2029 |
| 2025-02-14 | SRRTEP Western Item 06 - DEOK Supplemental Projects p. 7 |
Wilder-Decoursey DEOK-2025-001 |
Beaver Claryville Decoursey White Tower Wilder |
Status Engineering Cost $7,210,650 In service 10/19/2027 |
| 2025-02-14 | SRRTEP Western Item 07 - ATSI Supplemental Project p. 3 |
Ellsworth Substation – s1952 Scope Change s1952 |
Berlin Lake Boardman Canfield Steel Substation Canfield substation Ellsworth Substation Kimberly Salt Springs Victoria Road Weldon Substation New |
Status Pre-Engineering (Engineering) Cost $36.3M In service 4/30/2027 Load 19 MW |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 01 - PPL Supplemental Projects p. 3 |
Rutherford, PA PPL-2025-0001 |
Rutherford | In service 5/2026 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 02 - ACE Supplemental Projects p. 3 |
Pine Hill Substation ACE-2024-003 |
Pine Hill Sickler Stratford |
Status Conceptual Cost $27.4 M In service 9/1/2029 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 03 - Penelec Supplemental Projects p. 3 |
Glory – Nanty Glo – Spangler 46 kV Switches PN-2024-026 |
Belsano Glory Nanty Glo Spangler Strongstown Twin Rocks |
Status Conceptual Cost $1.86 M In service 11/13/2026 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 04 - JCPL Supplemental Projects p. 3 |
Werner Substation JCPL-2024-033 |
Raritan River Substation Werner Substation |
Status Conceptual Cost $0.7 M In service 03/31/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 04 - JCPL Supplemental Projects p. 5 |
Werner Substation Customer Connection JCPL-2024-035 |
Raritan River Substation Werner Substation |
Status Conceptual Cost $0.5 M In service 03/31/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 3 |
Waugh Chapel Circuit Breaker B4 BGE-2024-002 |
Waugh Chapel | Status Engineering Cost $0.7M In service 4/10/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 5 |
Waugh Chapel Circuit Breaker B7 BGE-2024-003 |
Waugh Chapel | Status Engineering Cost $0.7M In service 10/9/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 7 |
Waugh Chapel Circuit Breaker B10 BGE-2024-004 |
Waugh Chapel | Status Engineering Cost $0.7M In service 5/15/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 9 |
Waugh Chapel Circuit Breaker B12 BGE-2024-005 |
Waugh Chapel | Status Engineering Cost $0.7M In service 11/13/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 11 |
Windy Edge Circuit Breaker B3 BGE-2024-006 |
Windy Edge | Status Engineering Cost $0.7M In service 4/3/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 13 |
Windy Edge Circuit Breaker B4 BGE-2024-007 |
Windy Edge | Status Engineering Cost $0.7M In service 5/8/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 15 |
Windy Edge Circuit Breaker B24 BGE-2024-008 |
Windy Edge | Status Engineering Cost $0.7M In service 12/11/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 17 |
Windy Edge Circuit Breaker B28 BGE-2024-009 |
Windy Edge | Status Engineering Cost $0.7M In service 10/2/2025 |
| 2025-02-13 | SRRTEP Mid-Atlantic Item 05 - BGE Supplemental Projects p. 19 |
Granite Circuit Breaker B2 BGE-2024-010 |
Granite | Status Engineering Cost $0.7M In service 5/1/2025 |
| 2025-02-04 | TEAC Item 04 - ATSI Supplemental Project p. 3 |
Lallendorf, OH ATSI-2025-005 |
Lallendorf Substation Laplaisance Creek New Monroe |
In service 6/1/2032 |
| 2025-02-04 | TEAC Item 04 - ATSI Supplemental Project p. 4 |
Lemoyne, OH ATSI-2025-004 |
Laplaisance Creek New Lemoyne Majestic Maple |
In service 6/1/2032 |
| 2025-02-04 | TEAC Item 05 - APS Supplemental Project p. 3 |
APS Transmission Zone M-3 Process Frederick, MD/Monocacy, MD APS-2025-001 |
Frederick A Substation Monocacy Substation |
No figures printed |
| 2025-02-04 | TEAC Item 06 - JCPL Supplemental Projects p. 3 |
Glen Gardner No. 2 230-34.5 kV Transformer JCPL-2024-043 |
Glen Gardner | Status Conceptual Cost $7.5 M In service 05/01/2025 |
| 2025-02-04 | TEAC Item 06 - JCPL Supplemental Projects p. 5 |
Larrabee No. 3 230-34.5 kV Transformer JCPL-2024-023 |
Larrabee | Status Conceptual Cost $7.3 M In service 04/12/2027 |
| 2025-02-04 | TEAC Item 07 - Dayton Supplemental Projects p. 3 |
Dayton-2025-001 | Fayette | In service 1/2031 Load 1.5 GW |
| 2025-02-04 | TEAC Item 07 - Dayton Supplemental Projects p. 4 |
Dayton-2025-002 | Clinton | In service 1/2030 Load 500 MW |
| 2025-02-04 | TEAC Item 08 - PPL Supplemental Projects p. 3 |
PPL Transmission Zone: Supplemental S0867.1 |
Dauphin Substation | Status Engineering Cost $1.1M In service 12/31/2026 |
| 2025-02-04 | TEAC Item 09 - PECO Supplemental Projects p. 3 |
Peach-Bottom Unit #2 Relay Replacement PE-2024-007 |
Peach Bottom | Status Complete Cost $836,000 In service 11/3/2024 |
| 2025-02-04 | TEAC Item 10 - DEOK Supplemental Projects p. 3 |
New Customer Load Request DEOK-2025-002 |
Beckjord Power Station | In service 2028 Load 300 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 4 |
Duval 230kV Delivery - DEV DOM-2024-0031 |
Duval New Midlothian Winterpock |
Status Engineering Cost $30.0M Substation, $80M Transmission Lines In service 1/1/2028 Load 100 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 6 |
Replace Landstown TX#1 - DEV DOM-2024-0086 |
Landstown | Status Engineering Cost $5.1 M In service 12/31/2025 |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 8 |
Replace Landstown TX#2 - DEV DOM-2024-0087 |
Landstown | Status Engineering Cost $4.76 M In service 12/31/2026 |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 10 |
Mountain Run 230kV Delivery - REC DOM-2022-0034 |
Cirrus New Culpeper Kyser New Mountain Run Mountain Run Junction Technology New |
Status Engineering Cost $60 M In service Q4 2027 Load 298 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 12 |
Palomino 230kV Delivery - DEV DOM-2024-0085 |
Cirrus Palomino Sub New |
Status Conceptual Cost $38.6M In service Q2 2028 Load 100 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 14 |
Chandler 230kV Delivery - DEV DOM-2024-0082 |
Chandler Sub New Palomino Sub |
Status Conceptual Cost $20.8M In service Q2 2028 Load 100 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 16 |
McDevitt 230kV Delivery - DEV DOM-2024-0083 |
Chandler Sub McDevitt New |
Status Conceptual Cost $19.8M In service Q2 2028 Load 100 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 18 |
Mt Pony 230kV Delivery - DEV DOM-2024-0084 |
McDevitt Mt. Pony Sub New |
Status Conceptual Cost $39.8M In service Q2 2028 Load 100 MW |
| 2025-02-04 | TEAC Item 11 - Dominion Supplemental Projects p. 20 |
Do No Harm Analysis DOM-2024-0084-DNH |
Oak Green Sub Potato Run Remington |
Status Conceptual Cost $140.8M In service Q2 2028 |
| 2025-02-04 | TEAC Item 12 - Reliability Analysis Update p. 10 |
b3737.41 Cancellation: Windsor – Clarksville 230kV b3737.41 |
Clarksville JCPL East Windsor Switch Windsor |
Status Cancellation (Cancelled) Cost $1.49M |
| 2025-02-04 | TEAC Item 12 - Reliability Analysis Update p. 11 |
b2003 Cancellation: Whippany – Montville 230kV b2003 |
Montville Whippany |
Status Cancellation (Cancelled) Cost $37.5 M |
| 2025-02-04 | TEAC Item 12 - Reliability Analysis Update p. 13 |
Brandon Shores Deactivation Project Updates: Summary of Cost Changes b3780.1 |
Batavia Road New Bramah Brighton Burchess Hill Conastone Cooper Doubs Graceton Granite New North Delta New Peach Bottom Peach Bottom North Peach Bottom South Riverside Solley Road New West Cooper New |
Cost 1513.96 In service 12/31/2028 |
| 2025-02-04 | TEAC Item 12 - Reliability Analysis Update p. 16 |
NJ State Agreement Approach Project Update b3737.22 |
Larrabee Collector station New Smithburg |
Cost $208.9M In service 12/31/2027 |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.