Substation Scout

Pratts

Named in 2 PJM planning documents for 2 projects, from November 15, 2024 to June 17, 2026.

Not stateddescribed as
APSzone
115 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gordonsville – Pratts 115 kV Line
APS-2024-092
Not printed Not printed Not printed Not printed 2024-11-15
SRRTEP Western
Misoperation Relay Projects
APS-2026-032
Not printed Not printed Not printed Not printed 2026-06-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-06-17 SRRTEP Western
Item 03 - APS Supplemental Projects p. 12
Misoperation Relay Projects No role wording
115 kV
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 6
Gordonsville – Pratts 115 kV Line No role wording
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this