Substation Scout

Darbyville

Named in 2 PJM planning documents for 2 projects, from October 18, 2024 to November 15, 2024.

Not stateddescribed as
AEPzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline Beatty 69kV Cap Bank
b3880.1
Not printed $2.25M 6/1/2029 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline Beatty 69kV Cap Bank Not printed $2.25M 6/1/2029 Not printed 2024-10-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 34
AEP Transmission Zone: Baseline Beatty 69kV Cap Bank No role wording
69kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 33
AEP Transmission Zone: Baseline Beatty 69kV Cap Bank No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this