Mentions: May 2026
Each row is one PJM document naming substations for one project, newest first. Atom feed
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
| Date | Document | Project | Substations named | As printed |
|---|---|---|---|---|
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 3 |
South East Canton, OH AEP-2025-OH020 |
South Canton Southeast Canton Sunnyside Timken Timken Richville Torrey Vettel New |
Status Engineering Cost $33.07M In service 01/07/2028 Load 312MW |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 6 |
Falcon, KY AEP-2026-AP002 |
Falcon | No figures printed |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 7 |
Kenova, WV AEP-2026-AP004 |
Kenova | No figures printed |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 8 |
Botetourt, VA AEP-2026-AP006 |
Botetourt | Load 300 MW |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 10 |
Illinois Road, IN/Gateway, IN AEP-2024-IM012 |
Conrail SW New Gateway Illinois Rd |
Status Engineering Cost $55.628 M In service 08/15/2030 |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 12 |
Wayne County, WV AEP-2022-AP032 |
East Lynn Lavalette Tri-State |
Status Scoping (Conceptual) Cost $98.8 M In service 11/28/2029 |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 14 |
Thelma, KY/Big Sandy, KY/Busseyville, KY AEP-2025-AP006 |
Big Sandy Busseyville Thelma |
Status Scoping (Conceptual) Cost $169.555 M In service 11/01/2030 |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 16 |
Progress Park, VA AEP-2026-AP001 |
Progress Park | Status Engineering Cost $11.759 M In service 02/08/2027 Load 240MW |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 18 |
South Canton, OH/Torrey, OH AEP-2025-OH007 |
Petros New South Canton Timken Richville Torrey |
Status Engineering Cost $49.124 M In service 10/13/2027 Load 255 MW |
| 2026-05-15 | SRRTEP Western Item 01 - AEP Supplemental Projects p. 20 |
Muskingum River, OH AEP-2025-OH013 |
Muskingum Muskingum River |
Status Conceptual Cost $5.782 M In service 12/06/2027 Load 200MW |
| 2026-05-15 | SRRTEP Western Item 02 - AMPT Supplemental Projects p. 3 |
Harmon-Brewster 69kV line AMPT-2026-002 |
Alpine Brewster Harmon |
No figures printed |
| 2026-05-15 | SRRTEP Western Item 02 - AMPT Supplemental Projects p. 4 |
Bremer-East Leipsic 69 kV line AMPT-2026-003 |
Bremer East Leipsic |
No figures printed |
| 2026-05-15 | SRRTEP Western Item 02 - AMPT Supplemental Projects p. 5 |
Kexon Tap-Kidston-Chase Brass 69 kV line AMPT-2026-004 |
Chase Brass Kexon Kexon Tap Kidston Snyder Substation |
No figures printed |
| 2026-05-15 | SRRTEP Western Item 03 - APS Supplemental Projects p. 3 |
Belmont - Long Reach 138 kV Line APS-2026-017 |
Belmont Eureka Substation Long Reach Pleasants Power Station |
Load 3 MW |
| 2026-05-15 | SRRTEP Western Item 03 - APS Supplemental Projects p. 4 |
New Customer Request APS-2026-019 |
Double Toll Gate Millville |
In service 10/03/2027 Load 13 MW |
| 2026-05-15 | SRRTEP Western Item 03 - APS Supplemental Projects p. 6 |
Loughs Lane – Pickens 138 kV Line APS-2023-032 |
Beverly Substation Beverly Tap Durbin Substation Durbin Tap Loughs Lane Substation Pickens |
Status Conceptual Cost $182.84M In service 11/04/2032 |
| 2026-05-15 | SRRTEP Western Item 03 - APS Supplemental Projects p. 9 |
Gordon – Nyswaner 138kV Line APS-2024-055 |
Gordon Manifold Nyswaner Perryman |
Status Conceptual Cost $30.12M In service 12/29/2028 |
| 2026-05-15 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 3 |
Ashtabula-Leroy Center 138 kV Q-1, Q-2, Q-3, and Q-4 lines ATSI-2026-031 |
Ashtabula Austinburg Leroy Center Sanborn Spruce Stacy |
No figures printed |
| 2026-05-15 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 7 |
Ivy 138 kV Substation ATSI-2026-036 |
Inland Ivy Substation Juniper Newburgh |
Load 29 MW |
| 2026-05-15 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 8 |
New Customer Request ATSI-2026-039 |
Brookside Henrietta |
In service 7/30/2027 Load 16 MW |
| 2026-05-15 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 10 |
Bulk Mail Facility 138 kV ATSI-2026-002 |
Bulk Mail Facility Fernway Fernway Tap Pine |
Status Conceptual Cost $1.69M In service 12/31/2027 |
| 2026-05-15 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 12 |
Dixie 69 kV Substation ATSI-2026-005 |
Dixie Substation Omni Perstorp Perstorp Polyols Teledyne |
Status Conceptual Cost $3.43M In service 12/31/2027 |
| 2026-05-15 | SRRTEP Western Item 05 - DLCO Supplemental Projects p. 3 |
Brunot Island Substation DLC-2026-001 |
Brunot Island | Status Planning (Conceptual) Cost $0.825 M In service 12/31/2026 |
| 2026-05-15 | SRRTEP Western Item 06 - DEOK Supplemental Projects p. 3 |
Mt. Healthy Substation Rebuild DEOK-2026-002 |
Finneytown Mapleknoll Mt. Healthy Terminal Willey |
Status Scoping (Conceptual) Cost $8.6M In service 05/07/2029 |
| 2026-05-15 | SRRTEP Western Item 07 - ComEd Supplemental Projects p. 3 |
138 kV L1210 Circuit Switcher ComEd-2026-008 |
None named | No figures printed |
| 2026-05-15 | SRRTEP Western Item 07 - ComEd Supplemental Projects p. 5 |
Wempletown ComEd-2026-007 |
Wempletown | Status Construction (Under construction) Cost $670k In service 5/22/2026 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 01 - BGE Supplemental Projects p. 3 |
Dorsey Run BGE-2026-002 |
Dorsey Run | Load 20 MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 01 - BGE Supplemental Projects p. 4 |
Perryman to Edgewood Rebuild BGE-2026-003 |
Edgewood Perryman |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 01 - BGE Supplemental Projects p. 5 |
Granite to Chestnut Hill Rebuild BGE-2026-004 |
Chestnut Hill Granite |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 01 - BGE Supplemental Projects p. 6 |
Granite 230-1 BGE-2026-005 |
Granite | No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 02 - DPL Supplemental Projects p. 3 |
DPL-2026-001 | Cheswold Kent |
Status Engineering Cost $625,000 In service 06/07/2026 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 03 - PECO Supplemental Projects p. 3 |
PE-2026-011 | Crescentville Waneeta |
Status Construction (Under construction) Cost $350k In service 9/10/2026 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 3 |
Manitou- Ortley Beach- Seaside Park 34.5 kV D212 Line, NJ JCPL-2026-009 |
Lavallette Manitou Ortley Beach Seaside Heights Seaside Park Toms River |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 5 |
Larrabee - Point Pleasant B106 34.5 kV Line - New Customer Connection, NJ JCPL-2026-011 |
Larrabee Point Pleasant |
In service 12/13/2030 Load approximately 11 MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 6 |
Rockaway - West Wharton 34.5 kV I711 Line, NJ JCPL-2026-015 |
Beach Glen Beaver Brook Hewlett Packard Joyce Molding Mt. Hope Record Rockaway Rockway West Wharton |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 9 |
Manitou Substation, NJ JCPL-2026-016 |
Manitou Motts Corner |
Load approximately 25 MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 11 |
Cookstown Substation, NJ JCPL-2026-019 |
Cookstown Van Hiseville |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 13 |
Deep Run – Englishtown 115 kV DRE2 Line, NJ JCPL-2023-056 |
Deep Run Substation Englishtown |
Status Conceptual Cost $36.34M In service 05/18/2029 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 15 |
Deep Run – Englishtown 115 kV DRE1 Line, NJ JCPL-2023-066 |
Deep Run Substation Englishtown |
Status Conceptual Cost $38.88M In service 05/19/2028 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 06 - MetEd Supplemental Projects p. 3 |
Jackson Substation, PA ME-2026-002 |
Bair T Hamilton 115 kV Substation Jackson JE Baker Menges Mill |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 06 - MetEd Supplemental Projects p. 5 |
Hill - Jackson 115 kV 969 Line – New Customer Connection, PA ME-2026-006 |
Hill Jackson |
In service 4/1/2028 Load 22 MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 06 - MetEd Supplemental Projects p. 7 |
Frystown – South Lebanon 69 kV Line, PA ME-2024-022 |
Frystown Rehrersburg South Lebanon |
Status Conceptual Cost $32.59M In service 12/14/2029 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 07 - Penelec Supplemental Projects p. 3 |
Goudey – Tiffany/Warriner Pond 115 kV LG2 Line, PA PN-2026-005 |
Goudey Laurel Lake Tiffany Warriner Pond |
No figures printed |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 3 |
PPL Transmission Zone: Supplemental
Milford, PA PPL-2026-0032 |
Milford | In service 11/30/2030 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 4 |
PPL Transmission Zone: Supplemental
Allentown, PA PPL-2026-0035 |
None named | Load 75MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 5 |
PPL Transmission Zone: Supplemental
Macungie, PA PPL-2026-0036 |
None named | Load 15MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 7 |
PPL Transmission Zone: Supplemental
Woolrich, PA PPL-2026-0006 |
Lock Haven Lycoming Woolrich |
Status Conceptual Cost $2.1 M In service 11/30/2028 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 9 |
PPL Transmission Zone: Supplemental
Northampton, PA PPL-2026-0015 |
None named | Status Conceptual Cost $1.5 M In service 07/31/2027 Load 100 MW |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 11 |
PPL Transmission Zone: Supplemental
Dupont, PA PPL-2026-0019 |
Dupont Jenkins Scranton |
Status Conceptual Cost $0.9 M In service 11/30/2028 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 13 |
PPL Transmission Zone: Supplemental
Hosensack, PA PPL-2026-0025 |
Hosensack | Status Conceptual Cost $3.4 M In service 11/30/2028 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 15 |
PPL Transmission Zone: Supplemental
Port Carbon, PA PPL-2026-0026 |
Frackville Orwigsburg Port Carbon |
Status Conceptual Cost $7.2 M In service 11/30/2028 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 17 |
PPL Transmission Zone: Supplemental
Allentown, PA PPL-2026-0033 |
Hosensack Quarry South Allentown |
Status Conceptual Cost $3.6 M In service 01/30/2028 |
| 2026-05-14 | SRRTEP Mid-Atlantic Item 08 - PPL Supplemental Projects p. 19 |
PPL Transmission Zone: Supplemental
Quarry, PA PPL-2026-0034 |
Quarry Sands |
Status Conceptual Cost $1.3 M In service 11/30/2029 |
| 2026-05-14 | SRRTEP Southern Item 04 - DOM Supplemental Projects p. 4 |
115 kV Mayo Dunbar DP Modification – EMC-EMC DOM-2025-0022 |
Beech Branch Cool Springs Mayo Dunbar DP |
Status Construction (Under construction) Cost $1.9M In service 5/31/2026 Load 9.2 MW |
| 2026-05-14 | SRRTEP Southern Item 04 - DOM Supplemental Projects p. 6 |
Cradock – 115kV Delivery – Upgrade TX#2 - DEV DOM-2025-0080 |
Cradock Substation | Status Engineering Cost $0.33M In service 04/30/2027 Load 18 MW |
| 2026-05-14 | SRRTEP Southern Item 04 - DOM Supplemental Projects p. 8 |
115 kV Line #26 (Buena Vista-Rockbridge) EOL Rebuild DOM-2025-0091 |
Balcony Falls Buena Vista substation Lexington Rockbridge |
Status Engineering Cost $15M In service 12/31/2027 |
| 2026-05-08 | TEAC Item 03 - Penelec Supplemental Projects p. 3 |
Marshall - Moshannon 230 kV Line, PA PN-2026-003 |
Marshall Moshannon |
No figures printed |
| 2026-05-08 | TEAC Item 03 - Penelec Supplemental Projects p. 5 |
Altoona - Bear Rock 230 kV AB Line, PA PN-2026-004 |
Altoona Bear Rock |
No figures printed |
| 2026-05-08 | TEAC Item 04 - AEP Supplemental Projects p. 3 |
Manilla Ridge, WV AEP-2026-AP005 |
None named | In service 9/2029 Load 1200 MW |
| 2026-05-08 | TEAC item 05 - Dayton Supplemental Projects p. 3 |
Dayton-2025-007 | Brown New Concord New Eldean Miami Patina Shelby West Milton |
Status Conceptual Cost $591.5M In service June 30th, 2032 Load 1400 MW |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 3 |
PPL Transmission Zone: Supplemental PPL-2025-0010 · S3818 |
Glen Brook Harwood Nescopeck Slykerville Susquehanna Tomhicken Tresckow |
Status Conceptual Cost $88.5M In service 5/30/2027 Load 1000 MW |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 7 |
Jerseytown, PA PPL-2026-0001 |
Glen Brook Jerseytown New Montour Saegers |
Status Project Development (Conceptual) Cost $109.2 M In service 05/30/2028 Load 1,500 MW |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 9 |
Callender Gap, PA PPL-2026-0002 |
Callender Gap Lackawanna |
Status Project Development (Conceptual) Cost $76.5 M In service 05/30/2029 Load 1,200 MW |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 11 |
Beach Haven, PA PPL-2026-0003 |
Beach Haven New Glen Brook Nescopeck Susquehanna Susquehanna T10 |
Status Project Development (Conceptual) Cost $81.2 M In service 05/30/2028 Load 1,500 MW |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 13 |
Nescopeck, PA PPL-2026-0004 |
Nescopeck Sunbury Susquehanna |
Status Project Development (Conceptual) Cost $130.6 M In service 05/30/2029 Load 1,350 MW |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 15 |
Hummelstown, PA PPL-2026-0022 |
Hummelstown | Status Conceptual Cost $7.1 M In service 12/31/2029 |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 17 |
Jenkins, PA PPL-2026-0023 |
Jenkins | Status Conceptual Cost $7.1 M In service 05/31/2029 |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 19 |
Hosensack, PA PPL-2026-0027 |
Hosensack | Status Conceptual Cost $4.9 M In service 11/30/2029 |
| 2026-05-08 | TEAC Item 06 - PPL Supplemental Projects p. 21 |
Steel City, PA PPL-2026-0028 |
Steel City | Status Conceptual Cost $3 M In service 11/30/2029 |
| 2026-05-08 | TEAC Item 07 - PECO Supplemental Projects p. 3 |
PE-2026-012 | Buckingham Warrington |
No figures printed |
| 2026-05-08 | TEAC Item 07 - PECO Supplemental Projects p. 5 |
PE-2026-006 | Cromby | Status Engineering Cost $115 M In service 06/01/2033 |
| 2026-05-08 | TEAC Item 08 - ComEd Supplemental Projects p. 2 |
Customer in Rockford ComEd-2025-014 |
None named | Load 600 MW |
| 2026-05-08 | TEAC Item 08 - ComEd Supplemental Projects p. 4 |
Nelson 345KV CB ComEd-2026-006 |
Nelson | Status Conceptual Cost $2.75M In service 12/31/2027 |
| 2026-05-08 | TEAC Item 09 - DOM Supplemental Projects p. 3 |
Equipment Material Condition, Performance and Risk DOM-2026-0019 |
Bremo Farmville |
No figures printed |
| 2026-05-08 | TEAC Item 09 - DOM Supplemental Projects p. 4 |
Operational Flexibility and Efficiency DOM-2026-0022 |
None named | Load 3000 MW |
| 2026-05-08 | TEAC Item 09 - DOM Supplemental Projects p. 6 |
Line #209 and Line #58 Partial Rebuild DOM-2021-0006 Update · s2623 |
Lebanon | Status Engineering Cost $66.89M In service 05/30/2029 Load 46.6MW |
| 2026-05-08 | TEAC Item 09 - DOM Supplemental Projects p. 8 |
Stockholm 230kV Delivery - DEV DOM-2024-0049 |
Stockholm New Thicket New |
Status Conceptual Cost $ 26M In service Q4 2028 Load 300 MW |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 11 |
AEP and DOM P5 CAPs: Baseline b4080.1 |
None named | In service 4/15/2030 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 13 |
PPL Transmission Zone: Baseline B4029.18 |
Susquehanna | Cost $7.39M |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 14 |
Dominion Transmission Zone: Baseline New 500kV Line North Anna - Thornburg - Bristers b4000.344 & b4000.345 |
Aquia Harbor Bristers Kraken New Ladysmith North Anna Stafford Thornburg New |
Cost $661.63M In service 9/16/2030 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 17 |
Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation B4000.355 – B4000.359 |
Anderson Branch Bristers Culpeper Yeat Elk Run Elmont Joshua Falls Kraken New Meadowbrook Morrisville Mosby Nokesville Possum Pt Spotsylvania Vint Hill Vontay New Wishing Star Yeat New |
Cost $1,109.89M In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 24 |
JCPL Transmission Zone: NJ SAA Baseline Project Cancelations b3737.2 |
Atlantic Freneau Lakewood Generator Substation Larrabee Larrabee Collector Station New Oceanview Red Bank Smithburg South Lockwood South River Substation |
In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 26 |
MAOD NJ SAA Baseline Project Cancelations b3737.22 |
Larrabee Collector station New Smithburg |
In service 12/31/2027 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 27 |
AE Transmission Zone: NJ SAA Baseline Project Cancelations b3737.26 |
Cardiff New Freedom |
In service 4/30/2028 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 28 |
JCPL Transmission Zone: NJ SAA Baseline Project Cancelations b3737.27 |
Clarksville Deans East Windsor Kilmer I Lake Nelson I Lawrence substation Middlesex Smithburg Windsor |
In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 29 |
JCPL Transmission Zone: NJ SAA Baseline Project Cancelations b3737.33 |
Kilmer Kilmer I Kilmer W Raritan River Substation Red Oak A Red Oak B |
In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 30 |
LS Power NJ SAA Baseline NJ Project Cancelations b3737.37 |
Hope Creek Silver Run |
In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 31 |
PSEG Transmission Zone: NJ SAA Baseline Project Cancelations b3737.40 |
Clarksville Windsor |
In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 32 |
PSEG Transmission Zone: NJ SAA Baseline Project Cancelations b3737.42 |
Greenbrook Kilmer Lake Nelson Middlesex |
In service 6/1/2029 |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 33 |
PECO Transmission Zone: NJ SAA Baseline Project Cancelation b3737.50 |
Bramah Conastone Delta York Furnace Run Peach Bottom |
In service 6/1/2029 |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.