Marley Neck
Named in 2 PJM planning documents for 2 projects, from November 6, 2024 to December 3, 2024.
Newdescribed as
BGEzone
115 kVkV as printed
2mentions
Described as new: “Construct new Marley Neck 115 kV substation” — source, page 43
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| BGE Local N-1-1 b3906.1 |
Not printed | $107.62M | 06/01/2029 | Not printed | 2024-12-03 TEAC |
| BGE Local N-1-1 | Not printed | Not printed | Not printed | Not printed | 2024-11-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $107.62M → 122.07 | 2024-12-03 | 2026-10-06 |
| Cost estimate prior value printed on the same page |
107.62 → 122.07 | 2026-10-06 | 2026-10-06 |
| Substations named | CHESTNUT HILL; FREDERICK RD; HOWARD; MARLEY NECK; NORTH EAST; PUMPHREY; WAGNER → MARLEY NECK | 2024-12-03 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2024-12-03 | TEAC Item 11 - Reliability Analysis Update p. 43 |
BGE Local N-1-1 | “Construct new Marley Neck 115 kV substation” 115 kV |
| 2024-11-06 | TEAC Item 13 - Reliability Analysis Update p. 43 |
BGE Local N-1-1 | “Construct new Marley Neck 115 kV substation” 115 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.