Substation Scout

Buchanan

Named in 2 PJM planning documents for 2 projects, from October 18, 2024 to November 15, 2024.

Existingdescribed as
AEPzone
138 kV, 138kVkV as printed
2mentions

Also printed as: Buchanan station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline Buchanan – Keen Mountain Upgrades
b3898.1
Not printed $0.1M 12/1/2025 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline Buchanan – Keen Mountain Upgrade Not printed $0.1M 12/1/2025 Not printed 2024-10-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 51
AEP Transmission Zone: Baseline Buchanan – Keen Mountain Upgrades “Upgrade the CT thermal limit at Buchanan station”
138kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 50
AEP Transmission Zone: Baseline Buchanan – Keen Mountain Upgrade “Upgrade the CT thermal limit at Buchanan station”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this